Construction Environmental 06683025-3000(AA)
Management Plan October 2006
Commercial Development

Rev: 000 Page 6
Eenie Creek Road, Noosaville

 

 

 

8.0 NON CONFORMANCE

Any non-conformance to the EMP must be addressed as soon as is practicable. The
personnel responsible for the non-conformance must be notified immediately for purposes of
issuing rectification instructions.

Non-conformances are formally documented through an audit report (Refer Section 11.3).

9.0 AUDITING OF THE EMP
9.1 Responsibilities

The construction activities at the development will be audited for compliance with the EMP
and its procedures by the environmental auditor. The environmental auditor will be
appointed by the Project Manager.

It is the environmental auditor’s responsibility to:

1. Provide an independent assessment of compliance with the Environmental
Procedures in Appendices A to F.

2. Report on observed activities that have, or may cause, an impact to the environment
or non-conformance to regulation.

3. | Provide recommendations to the Project Manager regarding practical initiatives that
can be employed to improve the effectiveness of environmental management at the
development site.

4. Provide a copy of the Environmental Audit Report to the project manager.

9.2 Frequency

The frequency of Environmental Audits from commencement of site construction activities
will be as follows:

¢ Every fortnight until the construction phase is completed.

10.0 COMMUNITY RELATIONS

Where concerns are made by the community or third parties to the Project Manager, or any
contractors under its control, these will be forwarded to the project manager immediately.

The process for dealing with concems is documented in Section 11.4.

Golder Associates

 

Used in these records

About this file

File size
10.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Application part 3 [As Published].pdf · 10.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.