fA Douglas Partners

“Page 9

. Any compacted silty or sandy silty clay foundation soil at or close to footing formation level
should be sealed or covered as soon as practicable, to reduce the opportunity for occurrence
of desiccation and cracking.

°. , ‘Level 1 tasting of filling, in ‘accordance with AS: 37984 j is recommended if the filling is to be
used for support of buildings and pavements.

The base of all soil trench excavations (if loosened) for any upper level strip and small pad footings
should be compacted by hand-guided compaction equipment such as ‘frog’ rammer or plate
vibrator, to the dry density. ratio as above. Where rock is exposed-.at the base of the trench
excavation, loose debris should be removed prior to pouring concrete.

in this report. To maintain’ compaction of thé batter,*iPis{yecommended that the fill platform be

Batters in any proposed controlled fill should be terns cr slope angles indicated tater
atter slope’

compacted in layers slightly wider than the. final
profile.

lignment, prior to’ trimming the final

  
   

  
 

The above procedures will require geotechnical inspection and .testit g services by qualified and
experienced geotechnical personnel during eee

lt should be noted that the investigation was Sin ned en inantly during dry weather and that the
high plasticity clays and near supe oils will durin prolonged wet weather or changes in
moisture condition and: may vol tin a ganity ee rigpilty problems, as indicated previously i in

   

_ this’ report.
7.7: Batter asope

Batter slopes cut to no dedper than m maviae designed for temporary and long term conditions as
presented inthe following table:
, Table 5 — Cut Batter Slopes

 

 

 

 

 

Materily” : Safe Batter Slope (H:V)
Short Term ‘Long Term

‘| Controlled Fill, Silty “Sand, ‘Stitt to, i an

Haid Clay :

‘Extremely low strength claystone and a 2

siltstone

Very low strength claystone and 0.75:1 1.5:1

siltstone _ :

 

 

 

 

 

The above temporary batter slopes are suggested with respect to slope stability only, and do not
allow for lateral.stress relaxation which may. result in movement of nearby inground services or
shallow footings. If such services are settlement-sensitive, and are located such that a linear spread
at 1H:1V outwards, down and away from the base of-the service,: intersects the cut face, then the
excavation’ may have to be positively supported.

The soil slopes may need to be flattened to 3H:1V or less, in order to allow vehicular access for
maintenance of grass.

* AS 3798-1996 Australian Standard “Guidelines on earthworks for commercial and residential developments’, Standards
Australia

 

Report on “Geotechnical Investigation . ° _ _ . Project 33984
Proposed Bunnings Warehouse, Eumundi-Noosa Road, Noosaville st . 16 August 2006

Used in these records

About this file

File size
3.8 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_2125 - Op Works - Bulk Earthworks [As Published].pdf · 3.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.