Attached to the e-mail 132007.2398.02 Request to change existing approval (2 of 3) Engineering report & plans, Stormwater Plan.
Plans and drawings: the text below has words only, no drawings.
Very large file (10.6 MB): may take a few minutes to open.
CALIBRE CONSULTING
Specific Outcomes Probable Solutions Proposed Measures
(if code assessable)
Existing services are relocated and the design and
construction of the relocated services is in accordance with
Sections 3, 4 and 5 of PSP 6 – Engineering Design Standards
– Water and Sewerage and Section 4 of PSP 5 – Engineering
Design Standards – Roads, Drainage and Earthworks.
O2 S2.1
Maintenance access is provided to all sewers, water A registered easement in favour of Council is created over all Due consideration will be given to the requirements of access
mains, stormwater drains, overland flow paths and underground infrastructure located in private property; for future maintenance throughout the detailed design
associated structures. AND process.
Preliminary consideration of these items have been provided
in the Drawings provided in this Report (No. B14158.W-02A
dated December 2014).
S2.2
The width of the easement is in the greater of 3m or the width
of the zone of influence;
AND
S2.3 N/A
The easement is centred over the centreline of the
infrastructure.
Table 7-5: Division 18: Transports, Roads and Drainage Code
B14158.W | COOROY RETIREMENT COMMUNITY | PALM LAKE RESORTS CIVIL ENGINEERING REPORT | 17
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
G ENGINEERING REPORT AND PLANS.pdfRelated documentApplication case desk ↗
About this file
- File size
- 10.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.