As shown in Table 3, the peak flow rate of stormwater runoff and the total runoff volume off site has
reduced as a result of the stormwater management system. The proposed infiltration/detention tank is
therefore considered to be adequate. Results for the 1% AEP, 10min duration event are outlined in
Figure 5 and 6 below.
Peak Flow measured at rear = 48L/s
Total runoff volume (Node A inflow)
= 24.58m3
Figure 5 - XP Storm Results; Pre-Developed Model (1% AEP, 10min Duration)
Peak Flow measured at rear = 46L/s
Total runoff volume
(Node A inflow + Node B outflow) = 16.75m 3
Figure 6 - XP Storm Results; Post-Developed Model (1% AEP, 10min Duration)
4 April 2019 Stormwater Management Report 9
S18-030 22 Arakoon Crescent,
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Stormwater Management Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 4.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.