Page 16 of 47

Task    Task Description          Sub-    Sub-task Description                   Linked       Resources    Council Leads      Approx.      Delivery    Deliverable / Outcome
 Toe                              Task                                           RoadMap                                       TTT ede)        a 4
                                  No.                                            ATC)
        Develop Risk                      Determine Asset Management System                                  Asset Planning    2 months — Short        AMS Risk Assessment needs
      Assessment                          risk / opportunity assessment                                      Coordinator,                              identified.
        Methodology and                   requirements.                                                       Governance
        Framework                                                                                            Advisor, Asset
                                                                                                             Management
                                                                                                             Steering Team
                                  2       Modify Council’s Corporate Risk           13.1       Council       Asset Planning        18      Short to    Revised corporate risk
                                          Assessment Approach, as necessary.                                 Coordinator,       Months     Medium | management approach.
                                                                                                              Governance
                                                                                                             Advisor, Asset
                                                                                                             Management
                                                                                                             Steering Team
        Develop Asset             1       Review of existing Council asset                                     Director        2 months                Opportunities to leverage existing
        Investment Planning               investment review / approval                                        Corporate                                processes/ tools. Any workflow
        Framework                        processes                                                           Services, Asset                           “gaps” identified.
                                                                                                             Management
                                                                                                             Steering Team
                                  2       Document the Asset Investment             14.1       Council         Director        4months     Medium | The Asset Investment Planning
                                          Planning Framework                                                   Corporate                               Framework.
                                                                                                             Services, Asset
                                                                                                             Management
                                                                                                             Steering Team
        Develop Asset                     Capture of asset management                          Council       Asset Planning    2 months    Medium | Contracts accurately and
        Management Delivery               requirements in Contracts.                                          Coordinator,                 to          consistently address asset
        Platform: Capture of                                                                                Procurement and                Long        management requirements
       Asset Management                                                                                      Fleet Manager,
        Requirements in                                                                                          Asset
        Contracts                                                                                            Management
                                                                                                             Steering Team
                                  2       Develop Guidelines for alternative        15.1       Council      Procurement and | 2 months | Long          Asset Management Contracting
                                          Forms of asset management                                          Fleet Manager,                            Guidelines
                                          contracting.                                                           Asset
                                                                                                             Management
                                                                                                             Steering Team
        Develop Asset             1       Develop corporate Project                                                                        Long
        Management Delivery               Management Framework (covering
        Platform: Develop                 asset management)
        Project Management                            -              -
       Approach for Asset         2       Develop and implement a Project
        Management                        Management training regime
        Develop Asset                     Ensure capture of asset management                   Council       Asset Planning    2 months | Short        PD Toolkit developed meets asset
        Management Delivery               requirements in existing PD Toolkit                                Coordinator,                              management requirements.
        Platform: Define Asset            initiative.                                                        Infrastructure
        Management Handover                                                                                Planning & Design
        Procedures                                                                                             Manager,
                                                                                                            Financial Services
                                                                                                               Manager,
                                                                                                              Coordinator
                                                                                                              Engineering.
                                  2       Document procedures for realisation                  Council       Asset Planning    4months | Short         Consistent approach to asset
                                          and capitalisation of handed-over                                  Coordinator,                              capitalisation that meets financial
                                          assets                                                             Infrastructure                            and operational requirements.
                                                                                                           Planning & Design
                                                                                                               Manager,
                                                                                                            Financial Services
                                                                                                               Manager
       Asset Management                   Develop a suitable template for future                             Asset Planning    2 months | Short        Draft Asset Management Plan
        Planning Platform:                Asset Management Plans                                             Coordinator,                              Template
        Develop and Agree on a                                                                                   Asset
        Standard Asset                                                                                       Management
        Management Plan                                                                                      Steering Team
       Template                                       -          =                                   =                 -                                  -
                                          Develop a “Pilot” AMP using the           18.1        Council      Asset Planning    4months | Short         Refined AMP Template and
                                          template developed to test / refine the             External        Coordinator,                             completed AMP
                                          template.                                            Provider          Asset
                                                                                                             Management
                                                                                                           Working Group(s)
       Asset Management           1       Capture and document existing asset     9.2, 18.1    Council       Asset Planning    2 months — Short        Existing asset strategies and their
        Planning Platform:               strategies.                                                         Coordinator,                              decision criteria
        Develop State of the                                                                  External           Asset
                                                                                               Provider
       Assets Report                                                                         (optional)      Management
                                                                                                             Steering Team
                                          Develop Asset-specific Levels of          19.1       Council       Asset Planning    12 months | Short       Asset Levels of Service
                                          Service                                                             Coordinator,
                                                                                                                 Asset
                                                                                                             Management
                                                                                                             Steering Team
                                          Develop State of the Assets Report                                 Asset Planning    2 months                SoAR Document
                                          (SoAR).                                                             Coordinator,
                                                                                                                 Asset
                                                                                                             Management
                                                                                                           Working Group(s)

                                                                                                                                                       Page 16 of 47
Log in to download the original file

2016-09-06 Services & Organisation Committee Agenda(PDF, 5MB).pdf · 5.4 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.