a. the landscape and rehabilitation works shown on the referenced landscape and
rehabilitation plans listed in this decision notice;
b. 8 x advanced trees to be planted within Zone 2C to the east of cabins 12-15 at 2m
spacings Species selected are to be in accordance with the plant species outlined
in the Rehabilitation Planting Schedule for the respective zones;
c. Upgrade the Blue Lilly Pilly (Syzygium oleosum or local native equivalent subject
to availability) from 60L to 100L;
d. Inter-planting of advanced Bangalow Palms (Archontophoenix cunninghamiana)
in the two eastern areas of Zone 2C including dense planting of understorey plants
Grasses and groundcovers planted at 1 plant per sq. meter;
e. All board walks must be constructed on elevated posts to allow for future root
zones of new trees and shrub planting beside the driveway to be maximised.
Where deemed possible by a qualified arborist post holes must be excavated
using exploratory vacuum excavation and it must be done so under arborist
supervision;
f. Inclusion of tree and shrub plantings to the east of cabins 6-14 inclusive within the
revegetation area 2a and 2b utilising 50mm tube stock and utilising native species
in accordance with the plant species outlined in the Rehabilitation Planting
Schedule for the respective zones. This should be undertaken at a rate of 1 tube
per 3 sq. metres;
g. Inclusion of mid-storey screening shrubs species along the road and entry road
frontage (revegetation areas 2a and 2b) to provide appropriate species diversity
and enhanced screening opportunities;
h. vegetated screening of any electrical transformers, bin storage and service areas
and the like from the road frontage;
i. control of all weed species listed in the following standards and legislation:
i. declared plants under the Land Protection (Biodiversity Act 2014 and sub-
ordinate Regulation 2016);
ii. Schedule 1, 2 and non-scheduled invasive species listed in the Noosa
Biosecurity Plan 2020, and any other species that pose a threat to the
integrity of the proposed regeneration.
42. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
Weed Management
43. The initial treatment of all woody weeds and vines (frangipani vine) must be commenced
within 3 months and be controlled within 9 months of the date of the development
approval being granted, and the following requirements must be complied with:
a) All trees at the site affected by the Frangipani Vine must be treated prior to 11 December
2025. This requirement applies regardless of whether the tree is to be removed at a later
date.
b) The Council is to inspect the site on 12 December 2025 to verify that the works have
been carried out.
c) A report on the effectiveness of the treatment is to be provided to the Council before 6
February 2026, and the Council is to inspect the site to verify the treatment before 13
February 2026.
8274014_1
3459-9154-4892, v. 1
8309250_1
8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.