GENERAL COMMITTEE MEETING AGENDA                                                        12 JULY 2021


   Early works requirements have been introduced to the delivery methodology to compress the
   overall delivery program by enabling relocations to occur concurrently with the design
   development. Other benefits include reducing the risk of authority interfacing with the main
   contractor (such as Energex and UnityWater) and having the ability to deliver authority
   relocation using specialist contractor’s, reducing risk of program and cost.

   The project consists of the following stages with the current status noted:

                                                                                               Cost
    Stage                        Description                   Timing      Status (%)
                                                                                             to Date

                                 Planning & detailed design   Mar 2020 –
    Planning & Design                                                         90%             $410,000
                                 including approvals           Jul 2021

    Implementation               Internal costs including     Mar 2020 –
                                                                              10%              $50,000
    Costs                        consultants                   Jun 2022

                                 Clearing Works               May 2021        100%             $70,000

                                 Energex relocation           June 2021       100%            $120,000
    Early Works
                                                              Jul 2021 –      This            For
                                 Trunk Watermain
                                                              Sep 2021      contract        approval

    Construction –
                                 All remaining works to       Oct 2021 –                       To be
    Main Civil Contract                                                      Design
                                 complete the upgrade         Jun 2022                       tendered
    (Future Works)

     Total to date                                                                            $650,000

   2.       Budget
   The overall budget for this project, under TMR’s Funding Agreement, is as follows:

                                                                                        Amount (Excl.
                                  Summary Financial Details
                                                                                               GST)

    Funding Agreement – Detailed Design Stage                                                 $600,000

    Funding Agreement – Construction Stage (Council’s Implementation
                                                                                              $485,000
    Costs)

    Funding Agreement – Construction Stage
                                                                                            $6,980,000
    (see breakdown below)

           Clearing                                                                           $80,000

           Energex relocation                                                                $313,500

           Trunk Watermain (This Contract)                                                   $767,480

           Main civil works                                                                $5,334,020

    Funding Agreement – TMR Costs                                                             $100,000

    Approved Variations                                                                             $0

    Contingency                                                                             $1,645,000

    TOTAL                                                                                   $9,810,000



                                                                                     Page 18 of 28
Log in to download the original file

2021-07-12 General Committee Meeting Agenda(PDF, 2MB).pdf · 1.7 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.