GENERAL COMMITTEE MEETING AGENDA 12 JULY 2021
Under the terms of the Funding Agreement, amounts exceeding the budget items requires
TMR approval to use the contingency. Under this Contract, any amount exceeding $767,480
requires TMR approval to access additional funds within the Contingency amount of
$1,645,000.
3. Tender Process
Due to the budget for the watermain relocation works being greater than $200,000, staff
prepared and called for public tenders in accordance with the Local Government Act 2009.
Tender T000042 was released via VendorPanel on 17 May 2021, and advertised in Noosa
Today on 21 May 2021. The tender closed on 15 June 2021 with seven (7) conforming
submissions received.
4. Tender Assessment
The tender evaluation panel undertook an assessment of the following conforming tender
submissions, listed in alphabetical order:
Diona Pty Ltd
Dormway Pty Ltd
GCE Contractors Pty Ltd
M&K Pipelines (QLD) Pty Ltd
Offaly Civil Pty Ltd
SGQ Pty Ltd
Silverstrand Development Pty Ltd
One additional submission was received and assessed as non-conforming and was not
considered.
The conforming tenderers were evaluated using the following evaluation criteria and
weightings:
Evaluation Criteria Weightings
Price 30%
Capability & Resourcing 15%
Contract Experience & Capacity 15%
Methodology 20%
Quality 10%
Health & Safety 5%
Contribution to Local Economy 5%
Note: Attachment 1 presents the evaluation outcome of the conforming submissions against
the above criteria.
The tender evaluation panel completed the evaluation process and considered M&K Pipelines
(QLD) Pty Ltd to be the most advantageous to Council, presenting the best value for money.
M&K Pipelines (QLD) Pty Ltd tender submission is most favourable based on their tender
demonstrating the following:
High level of experience and capability to construct trunk watermains for water
authorities, such as UnityWater.
A detailed methodology demonstrating their understanding of the scope.
Resourcing to commence as soon as awarded.
An advantageous program to complete work in a timely manner to enable the main civil
contract to commence as planned.
Certified Quality System.
Page 19 of 28