GENERAL COMMITTEE MEETING AGENDA 12 JULY 2021
Certified Workplace Health and Safety systems.
Overall best value for money benefit for Council.
5. Program & Next Steps
M&K Pipelines (QLD) Pty Ltd propose to commence procurement immediately in July with
Practical Completion towards the end of September 2021 inclusive of a wet weather allowance.
M&K Pipelines (QLD) Pty Ltd program duration is 10 weeks.
6. Construction Management & Inspections
The current delivery model has Council in the project management and Superintendent roles.
Council resourcing to support the project are in place with specialist consultants available to
provide technical advice and inspections if necessary.
Previous Council Consideration
Nil.
Finance
The estimated construction cost is fully funded by TMR under the Funding Agreement and
there will be no requirement to cashflow the costs.
As per the milestone payments nominated in the Funding Agreement, the first milestone
payment of $1.493M (ex GST) has been invoiced and will be paid to Council prior to the first
payment claim by the proposed contractor.
The total construction cost estimate is as follows:
Item Budget (Excl. GST)
M&K Pipelines (QLD) Pty Ltd (This contract) $554,795
Engineering consultants (if required, refer below)
Callaghan & Toth (engineering / designer) $5,000
Native Foresters (Fauna) $5,000
Archeo (Cultural Heritage) $10,000
Plant, equipment & labour (significant tree retention) $5,000
SUB-TOTAL $579,795
Budget $767,480
REMAINING BUDGET – Contingency Against Original Estimate
$187,685
under the Funding Agreement
Risks & Opportunities
Finance Risks Mitigation
Final contract value exceeds budget. Risk partly mitigated by a lumpsum contract.
Contingency using the original estimate under the
Funding Agreement is at 24% or $187,685. Under
the Funding Agreement, overall project contingency
(an additional $1.65M) is available if required
subject to TMR approval.
Page 20 of 28
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.