GENERAL COMMITTEE MEETING AGENDA                                                      28 APRIL 2014


14.   QUARTERLY OPERATIONAL PLAN PROGRESS REPORT

Author            Chief Executive Officer, Brett de Chastel
                  Executive Office

Index             ECM/ Subject/ Corporate Planning

Attachments       1.    Community & Development Operational Plan Report
                  2.    Community Infrastructure Operational Plan Report
                  3.    Executive Office Operational Plan Report
                  4.    Organisational Services Operational Plan Report



EXECUTIVE SUMMARY

Not applicable.

RECOMMENDATION

That Council note the report by the Chief Executive Officer to the General Committee dated 28
April 2014 in relation to progress with the implementation of the 2014 Operational Plan.



REPORT

At its meeting on 2 January 2014, the Council adopted its first Operational Plan. In the absence
of a Corporate Plan, this Operational Plan set the initiatives and activities to be dealt with by the
organisation during the first six months of operation.

Pursuant to the Local Government Act, the CEO is required to report to the Council on a
quarterly basis in relation to progress towards achieving the outcomes of the Operational Plan.
This report addresses progress from 1 January to 31 March 2014. Rather conveniently, that
period also coincided with our former Departmental structures and this report is presented on that
basis.

Overall progress

The table below sets out progress by Department and identifies the number and percentage of
activities that have either been completed or are on track. It also identifies the number and
percentage of activities that are not commenced.

                  Community &         Community        Organisational      Executive     Total
                  Development        Infrastructure      Services

Not Started       2 or 10%         6 or 21%            5 or 15%          13 or 26%       26 or 20%

On Track          16 or 80%        22 or 76%           22 or 70%         23 or 48%       83 or 64%

Completed         2 or 10%         1 or 3%             5 or 15%          13 or 26%       21 or 16%




                                                                                     Page 128 of 200
Log in to download the original file

2014-04-28 General Committee Meeting Agenda Pages 65-200(PDF, 6MB).pdf · 6.6 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.