Bligh Tanner Page 2 of 5
second intervals. At four locations across the site, saturated infiltration rates of 4.0, 4.2, 4.6 and
3.9 m/day were recorded, or an average rate of 170 mm/hr.
High infiltration rates are preserved in the design
• For 95% of the site, ground-level permeability is maintained.
• 68% of the site is free of structures, and significant amount of the site will remain
untouched by construction activities.
• 25% of the site is roofs, and most of the buildings are lightweight structures which sit on
raised piers, preserving ground-level permeability beneath them. Buildings are connected
via raised boardwalks rather than concrete pathways;
o 40% of roofs drain to tanks
o 40% of that water is used, primarily for toilet flushing (accounting for about a 0.4
ML/yr reduction in runoff volumes).
o All surplus roof water discharges to infiltration trenches beneath buildings (the
infiltration trenches have a 100 mm extended detention, are filled with clean
washed gravels, and have been incorporated into the structural design of the
building footings)
• Only 5% of the site consists on slab-on-ground construction. This was necessary to
provide for the Sound building (for acoustics), and part of the Create building sits on a
mounded area where it made sense to build directly onto natural surface. Roof runoff
from the roofs of slab-on-ground buildings is directed into infiltration trenches located
beneath adjoining buildings/boardwalks.
• 7% of the site is carpark, and a permeable gravel carpark pavement is proposed using the
Geobrics geoweb product (refer Figure 1 below).
Figure 1: Sample installation of ‘Geoweb’ trafficable permeable pavement at Hervey Bay.
High infiltration rates will be preserved post-construction
Construction activities have the potential to impact on the natural permeability of the site soils
through generation and inappropriate disposal of fine materials, silts and slurries, and excessive
compaction of soils. This will be managed on this site as follows:
• Construction drawings require infiltration tests to be conducted before and after
construction (refer drawing C001 and C100).
• Construction vehicle access will be limited to defined routes to minimise compaction,
although the infiltration rate of the site sands is likely to be fairly resilient to moderate
compaction.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
2013-05-09 Negotiated Decision Notice Request (MCU12-0133).pdfRelated documentApplication case desk ↗
About this file
- File size
- 314 KB (small file)
- File type
No other editions are linked here.