Bligh Tanner                                                                                   Page 2 of 5




second intervals. At four locations across the site, saturated infiltration rates of 4.0, 4.2, 4.6 and
3.9 m/day were recorded, or an average rate of 170 mm/hr.

High infiltration rates are preserved in the design
   • For 95% of the site, ground-level permeability is maintained.
   • 68% of the site is free of structures, and significant amount of the site will remain
       untouched by construction activities.
   • 25% of the site is roofs, and most of the buildings are lightweight structures which sit on
       raised piers, preserving ground-level permeability beneath them. Buildings are connected
       via raised boardwalks rather than concrete pathways;
            o 40% of roofs drain to tanks
            o 40% of that water is used, primarily for toilet flushing (accounting for about a 0.4
                ML/yr reduction in runoff volumes).
            o All surplus roof water discharges to infiltration trenches beneath buildings (the
                infiltration trenches have a 100 mm extended detention, are filled with clean
                washed gravels, and have been incorporated into the structural design of the
                building footings)
   • Only 5% of the site consists on slab-on-ground construction. This was necessary to
       provide for the Sound building (for acoustics), and part of the Create building sits on a
       mounded area where it made sense to build directly onto natural surface. Roof runoff
       from the roofs of slab-on-ground buildings is directed into infiltration trenches located
       beneath adjoining buildings/boardwalks.
   • 7% of the site is carpark, and a permeable gravel carpark pavement is proposed using the
       Geobrics geoweb product (refer Figure 1 below).




Figure 1: Sample installation of ‘Geoweb’ trafficable permeable pavement at Hervey Bay.


High infiltration rates will be preserved post-construction
Construction activities have the potential to impact on the natural permeability of the site soils
through generation and inappropriate disposal of fine materials, silts and slurries, and excessive
compaction of soils. This will be managed on this site as follows:
    • Construction drawings require infiltration tests to be conducted before and after
       construction (refer drawing C001 and C100).
    • Construction vehicle access will be limited to defined routes to minimise compaction,
       although the infiltration rate of the site sands is likely to be fairly resilient to moderate
       compaction.

Used in these records

About this file

File size
314 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

2013-05-09 Negotiated Decision Notice Request (MCU12-0133).pdf · 314 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.