ATTACHMENT 1 — CONDITIONS OF APPROVAL (Applied by the Assessment Manager)

 

ADMINISTRATIVE CONDITIONS

1. This development permit for building works relates only to the works described in the decision notice. It does
not include approval for any other building or structure that may be shown on the approved plans. Any
building work shown on the plans that is accepted development does not form part of this approval (building
work that is accepted development does not require an approval).

2. The conditions of approval overrules in any difference arising between it and the details shown on the
approved plans
3. In accordance with s94 of the Building Act 1975, this development approval will lapse if the building work has

not been completed and had a final certificate issued within 2 years from the date of approval (this is known as
the condition time).

4. In accordance with s73 of the Building Act 1975, the applicant must ensure a legible set of the approved
drawings for the building work is available on site while the building work is being carried out.

5. The building is not to be occupied until a final inspection has been carried out.

MANDATORY INSPECTIONS

6. The builder must ensure that Urban Certifiers is given a notice of inspection advising when the building work
has reached a stage that is ready for inspection. This notice must be given at least 48 hours prior to the
inspection being required, and by telephoning Urban Certifiers on (07) 5441 1777 or 0400 889 253, or by
emailing [email protected] notice is to be provided for the following stages:
(a) For the pool barrier — prior to filling the pool with water
(b) For the final stage — at completion of all aspects of the building work

The builder must not start the next stage of the work until they have been given a certificate of inspection for
the relevant stage, confirming that the stage complies with the building development approval.

If the builder does not give the required notice of inspection, Urban Certifiers is obliged by s29 of the Building
Regulation to advise the QBCC that the notice was not provided.

CERTIFICATES TO BE PROVIDED

7. Prior to a Final Inspection Certificate (Form 21) being issued for the building, a number of contractor and/or
consultant certificates are to be provided. These certificates must be from an approved competent person or a
QBCC licensee. The aspects requiring certification will be confirmed at the final inspection; however
certificates that are expected to be required are outlined in Attachment 2.

SPECIAL CONDITIONS

8. Unless approved by Council, any wall or fence must not exceed a height of 2m above natural ground level
(refer to notes on approved plans).

9. Unless approved by Council, the gatehouse must be setback 6m from the front boundary (refer to notes on the
approved plans).

10. Any works in the road reserve (on the nature strip) are not part of this approval and must be authorised by the
Noosa Council (i.e. the alterations to the driveway crossover, the landscaping and lighting).

STANDARD CONDITIONS
SITE PREPARATIONS

11. Any excavation or filling must be undertaken in a way that suitably prevents soil movement, generally by the
construction of retaining walls or suitable batter protection measures. Adequate support must be provided to
adjoining properties and buildings at all times during excavations and construction work.

12. Retaining walls or other types of soil retaining methods must be installed where the slope ratio for cut and or
fill is greater than that specified in Table 3.1.1.1 the BCA. Embankments that are to be left exposed at the end
of the construction works must be stabilised by landscaping to prevent soil erosion.

13. Retaining walls that exceed 1m in height require a building permit and must be designed by a registered
engineer.

 

 

7 AVOCET PARADE, PEREGIAN BEACH
PERMIT NO 8140 PAGE 2 OF 6

 

 

Used in these records

About this file

File size
16.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

7 avocet pde.pdf · 16.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.