1856-Construction Management Plan (Prelim V2) Oct 2020 - Barlow Shelley · OPW20/0145

of 27

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
CONTENTS

2.0      PROJECT DETAILS .......................................................................................................... 5
  2.1       Description ................................................................................................................... 5
  2.2       Extent of Works ............................................................................................................ 5
  2.3       Construction Timeline and Work Hours ...................................................................... 5
  2.4       Works Programme ....................................................................................................... 6

3.0      KEY PERSONNEL ............................................................................................................. 7
  3.1       Principal Details ........................................................................................................... 7
  3.2       Consulting Engineer Details ........................................................................................ 7
  3.3       Contractor Details ........................................................................................................ 7
  3.4       Administering Authority Details .................................................................................. 7
  3.5       Communication Protocol ............................................................................................. 8

4.0      CONSTRUCTION MANAGEMENT .................................................................................... 9
  4.1       Traffic Control & Parking ............................................................................................. 9
  4.2       Temporary Fencing & Pedestrian Movement ............................................................ 10
  4.3       Control of Emissions ................................................................................................. 10
  4.4       Water Quality .............................................................................................................. 10
  4.5       Mud and Dust Control ................................................................................................ 10
  4.6       Waste Management .................................................................................................... 10
  4.7       Erosion and Sediment Control .................................................................................. 10
  4.8       Protection of Existing Infrastructure ......................................................................... 11
  4.9       Existing Services........................................................................................................ 12
  4.10      Protection of Adjacent Properties ............................................................................. 12
  4.11      Workplace Health and Safety..................................................................................... 12
  4.12      Public Relations & Complaint Management .............................................................. 12

5.0      QUALITY CONTROL AND AUDIT INSPECTIONS........................................................... 13

6.0      LIMITATIONS OF THIS REPORT .................................................................................... 14

7.0      CLOSURE........................................................................................................................ 15




Preliminary Construction Management Plan                                                                                                3
October 2020

Used in these records

About this file

File size
3.0 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

1856-Construction Management Plan (Prelim V2) Oct 2020 - Barlow Shelley.pdf · 3.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.