24647 Seaview Tce Enviro Mgmt Plan
Attached to the e-mail MCU14/0084 Environmental Management Plan (71 Seaview Tce).
The original of this document is very large (18.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnNoosa Council documents
OPW16/0021
i. Contact details for the on-site manager.
ii. Dispute resolution procedures.
8. Traffic management during all aspects of the construct phase including shall be
generally in accordance with Sea View Terrace Traffic Management Plan and its
attachments (6 diagrams) prepared/compiled by Hutchinson Builders dated March
2016. The plan and its MUTCD must be amended prior to the prestart to include
this changes:
a. The proposed No Parking 6am-6pm workdays on the west side of Seaview
Terrace shall apply only to the last two parking spaces (ie approximately the
last 15m before the cul-de-sac head).
b. Maintenance of safe pedestrian access along Seaview Terrace at all time.
c. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Parked trucks must have engines turned off.
d. All reasonable efforts must be made to minimise impact on traffic flow and
the availability of parking spaces for local residents
9. If any additional parking or traffic restrictions are required on Seaview Terrace
these restrictions must be approved in writing by Council prior to the
implementation of any additional restrictions.
10. Any changes to the details associated with the supervising RPEQ or Principal
Contractor during construction, must be notified to council in writing within five
business days of the change occurring.
11. Any conflict between the development and an existing or proposed service must be
referred to the relevant service authority for determination prior to commencement
of works.
DURING CONSTRUCTION
Engineering
12. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to
assets must be repaired immediately where it creates a hazard to the community.
In circumstances where the damage does not create a hazard to the community, it
must be repaired immediately on completion of the works associated with the
development.
13. All works must be supervised by a Registered Professional Engineer of
Queensland (RPEQ) who is independent of the Developer and Principal
Contractor, and they must certify that all works conform to the Operational Works
permit.
14. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans and conditions detailed in this Decision Notice.
b. The relevant conditions of the higher order Material Change of Use approval
MCU14/0084 to which this approval relates.
c. All relevant Noosa Council Planning Scheme Policies and standard
specifications and guidelines.
Page 5 of 15
Document Set ID: 20097969
Version: 1, Version Date: 12/07/2016 Print Date: 12 July 2016, 2:14 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.