Skip to the record
Accept no substitutions.

Original source · versioned page text

24647 Seaview Tce Enviro Mgmt Plan

Attached to the e-mail MCU14/0084 Environmental Management Plan (71 Seaview Tce).

of 212

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (18.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
List of Referenced Legislation & Codes of Practice – Environment
HB-HSEQ-F-005-A Version 5
           Issues            Applicable Legislation / Guidelines / Standards   Regulating                       Major Requirements Of Legislation
                                                                                Authority

 Cultural Heritage          Heritage Act 1977                                  NSW EPA         The duty of care under the legislation protects not just registered cultural
                                                                                                heritage sites but all sites
                                                                                               A Cultural Heritage survey may be required, and for some projects a
                                                                                                Cultural Heritage Management Plan. An application for local
                                                                                                government approval may also need to be lodged.
                                                                                               Where sites have areas containing native remnant vegetation or areas
                                                                                                where no disturbance to the ground surface has occurred; cultural
                                                                                                heritage (Heritage and cultural heritage) may be present.
                                                                                               If it is suspected that an area may be of cultural importance, request a
                                                                                                search of the EPA Heritage Register(s) to see if the site is registered.
 Discovery of Bones or      Heritage Act 1977                                  NSW EPA         The duty of care under the legislation protects not just registered cultural
 Artefacts (Discovery of                                                                        heritage sites but all sites
 items of European or                                                                          The discovery of bones or artefacts must be reported to the EPA and
 Indigenous Cultural                                                                            the artefacts must not be interfered with.
 Heritage Discovery of
                                                                                               Any bones or artefacts found must be protected and conserved.
 Bones or Artefacts)
                                                                                               Aboriginal ownership of any items found must be recognised.
                                                                                               If items are uncovered that are suspected to be of cultural heritage
                                                                                                significance, cease work immediately and notify the EPA.
                                                                                               Do not move or disturb items or artefacts.
                                                                                               The Project manager should contact the Police if bones are discovered.
 Native Title               Native Title Act 1993 Commonwealth                 NSW EPA         Permission must be sought from Native Title holders for any work to be
                                                                                                conducted on land to which Native Title applies.
                                                                                               The site may be operating under an Indigenous Land Use Agreement
                                                                                                (ILUA).
 Noise and Vibration
 Sensitive Receptors        Protection of the Environment Operations (Noise    NSW EPA         Identify potential sensitive noise receptors prior to commencement of
                            Control) Regulations 2008                                           work. If present, consult with potential receptors and modify procedures
                                                                                                or timing to reduce impact.
                                                                                               Reduce the noise source sound pressure level.
                                                                                               Select a suitable location for any noise source taking advantage of any
                                                                                                attenuation provided by barrier structures or by providing a buffer.


                            AS/NZ 2436:2010 "Guide to Noise Control on         Australia       Methods for sound measurement and the control of noise are outlined
                            Construction, Maintenance and Demolition sites".   Standards       Guidelines provided for hearing protection
 Soil Management


HUTCHINSON BUILDERS                                                                                                                                                       16
Log in to download the original file

24647 Seaview Tce Enviro Mgmt Plan.pdf · 18.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.