Reference Document - Slope Stability Assessment - 51091.3953.02 (As Published) · 51901.3953.02
No design loadings were available at the time of reporting. Footings for the proposed extensions must
penetrate through any fill materials and unsuitable natural soils (i.e. very loose to loose sands) to found
at least 0.5 m into medium dense (or denser) sands. Based on the current borehole & DCP information,
footing depths in the order of about 2 m to 2.5 m BGL (below the existing ground levels) are expected.
Based on the proposed development plans, negligible earthworks will be required, and as such footings
will therefore need to be piled.
Given the site access constraints, screw piles using a mini rig could be a suitable option. Piles founded at
least 0.5 m into the medium dense (or denser) sands may be designed using an allowable end bearing
pressure (ABP) of 300 kPa. Footing design should also account for potential soil reactivity.
Due to the likely presence of loose sands, together with the close proximity to surrounding infrastructure,
open bored piers or driven piles are not considered to be appropriate for this site. Steel reinforced
concrete bored piles could be feasible; however, the use of sacrificial liners (e.g. ‘formatube’) would be
required to prevent the caving of upper loose sands.
The advice of a specialist piling contractor must be sought regarding feasibility, design and installation of
the piling system for this site, including an assessment of potential vibration effects on nearby structures,
and monitoring requirements.
If steel screw piles are adopted, it will be important to ensure close supervision of installation, as piling
may not encounter sufficient drilling resistance (from torque measurement) in sands at the suggested
founding depth and piles could extend to much greater depth than necessary.
It is therefore recommended that site-specific load testing be conducted on screw piles, if adopted, at a
minimum. Where tension or compression capacity developed in the footings is critical for the future
structure (e.g. resistance to uplift forces from high winds), then cyclic load tests (including measurement
of deflections under tension and compression cycles) should also be undertaken prior to construction.
Kentledge for static testing, or simulated cyclic loads, should prove the piles to a minimum of two times
the expected working load within tolerable deflections.
All footings should found such that they are not adversely affected by (or affect) any adjacent
excavations, trenches or retaining walls that are not designed to support building loads. Footings should
found at least below a plane extending 1 m horizontally from the base of trenches/excavations/retaining
walls, then rising up at 1V:1H, as illustrated in Text Figure 10.
Where footings are located within a horizontal distance of 1.5H (H being the batter height) of any cut or
fill batter crest, these footings must be founded at a depth level with the toe of the batter.
Text Figure 10: Zone of influence diagrams – footings to be founded below these lines
If bored piles are adopted, it is recommended that footings be inspected by an RPEQ prior to placement
of steel reinforcement and pouring of concrete to confirm allowable bearing pressures and cleanliness of
excavations.
20 November 2025
25364-001-Rev0 10 of 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Reference Document - Slope Stability Assessment - 51091.3953.02 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 4.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.