Decision Notice - OPW22 0251 [As Published]

of 38

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

2211-31930 SRA

 

Permit and License Management
GPO Box 2454
Brisbane Qid 4001

Note: Appropriately qualified person(s) means a person or persons
who has professional qualifications, training, skills and experience
relevant to soil chemistry or acid sulfate soil management and can
give authontative assessment, advice and analysis in relation to acid
sulfate soil management using the relevant protocols, standards,
methods or literature.

 

Remove and dispose of the existing access ramp at an appropriately
licenced facility that accepts such waste.

Within three months of
commencement of the
demolition

 

admini

10.6.3.3.1.1 — Operational work involving marine plants— The chief executive
Planning Act 2016 nominates the Director-General of Department of Agriculture and Fisheries to be
the enforcement authority for the development to which this development approval relates for the
istration and enforcement of any matter relating to the following conditions:

administering the

 

8.

Development is limited to permanently remove, damage, destroy
marine plants within 22.5m? as shown in Table 1: Permanent impacts
to marine plants and Figure 2: Proposed marine plant impacts at
Catalina Jetty of the report titled Marine Plant Assessment — Catalina
Jetty, Gympie Terrace, Noosaville Retaining Wall Upgrade prepared
by Native Foresters, dated 27" April 2023 and document no 230427
(as amended in red by SARA on 17 July 2023).

At all times

 

Development is limited to temporarily remove, damage, destroy
marine plants within 209.15 m? as shown in Table 2: Temporary
impacts to marine plants and Figure 2: Proposed marine plant
impacts at Catalina Jetty of the report titled Marine Plant Assessment
— Catalina Jetty, Gympie Terrace, Noosaville Retaining Wall
Upgrade prepared by Native Foresters, dated 27" April 2023 and
document no 230427 (as amended in red by SARA on 17 July 2023).

At all times

 

10.

The revetment reconstruction and sediment stabilisation must be
camied out generally in accordance with the following plans:

(a) General Arrangement Plan and Details prepared by Long View
Consulting Engineers, dated Jan 2023, drawing number S020 and
revision P3

(b) Sections and Details prepared by Long View Consulting
Engineers, dated May 2023, drawing number S030 and revision P2.

At all times

 

11.

Maintain the development in accordance with the plans referenced in
condition 10, and the requirements of any conditions included in this
referral agency response.

At all times

 

12.

Submit written notice to the Department of Agriculture and Fisheries
at [email protected] advising when the development
authorised under this referral agency response:

(a) will start

(b) when it has been completed.

Any notice must state the application's reference number: 2211-
31930 SRA.

(a) At least 5 business
days but no greater
than 20 business days
prior to the
commencement of the
works

(b) Within 15 business
days of the completion
of the fisheries
development works

 

13.

 

 

Spoil is not disposed of on tidal lands or within waterways and is

At all times

 

 

State Assessment and Referral Agency

Document Set ID: 22549959

Version: 4, Version Date: 23/08/2023

Page 5 0f0

Page 11 of 38

 
Log in to download the original file

Decision Notice - OPW22 0251 [As Published].pdf · 5.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.