Decision Notice - Minor Change - 132007 12 9 [As Published]
Pathway Lighting
41. The existing pathway between the two existing lots shall have lighting installed from
Goodchap Street to the rear boundary of Lot 4. This lighting shall have a high energy
efficient rating to the reasonable satisfaction of Council and be designed to meet
appropriate safety standards and not to adversely impact residences in the area.
Vegetation Protection & Preservation
42. Vehicular pavements within the drip zone of any of the existing trees on site to be
retained shall be designed as a pervious pavement (such as grass paving cells or
similar), as this will allow water that falls on this surface to penetrate to the trees root
system. The pavement shall be constructed so as not to damage the tree or their root
system and in this regard temporary fencing shall be provided around the trees during
construction to help protect them.
Plans shall be submitted to the Council for approval that clearly show the type and extent
of the pervious pavement and the temporary fencing prior to obtaining a Development
Permit for Operational Works.
Frontage Works
43. Tree planting is required to the Goodchap Street frontage of Proposed Lot 5 in
accordance with Planning Scheme Policy PSP03 Landscaping Plants & Guidelines.
Roof Water & Stormwater Drainage
44. Stage A - Roof runoff from any new building shall be directed to a rainwater storage
system or tank (minimum storage the greater of 5000 litres or 15 litres/m2 of roof area)
that is installed to ensure water from the tank is used for external uses (such as watering
gardens, irrigation, ornamental ponds, water features, outdoor cleaning, etc) and for use
in flushing of toilets internal to the building. All rainwater tanks are to be designed and
installed in accordance with the Queensland Development Code (QDC), Part 25 -
Rainwater Tanks, and shall be part of the plumbing application in conjunction with the
building approval. The location and capacity of the tanks shall be clearly shown on the
plans submitted for Building Works / Operational Works approval and any overflow shall
be directed to an approved discharge point.
All stages:
45. All stormwater drainage (including roof water overflow from the rainwater storage
system) must be collected and discharged so there is no net increase in stormwater
runoff from the site.
46. A Stormwater Management Plan must be submitted to Council in conjunction with an
operational works application to demonstrate how water quality and quantity objectives
are to be met as follows:
• No increase in peak flow runoff from the site up to and including a one in 100 year ARI.
• 80% reduction in total suspended solids;
• 60% reduction in total Phosphorus
• 45% reduction in total Nitrogen compared to an unmitigated development scenario.
This Management Plan must set the objectives and include a plan indicating location
and sizing of the devices prosed. The operational works application shall be in
accordance with this plan and buildings must be modified if required to accommodate the
treatment infrastructure wholly within the allotment.
A maintenance plan for the treatment devices must be complied with for the duration of
the approved uses.
A Development Permit for Building Works must not be granted until a Development
Permit for Operational Works has been issued in regard to the drainage scheme.
Page 6 of 18
Document Set ID: 22465906
Version: 7, Version Date: 22/06/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original