               47.    All site stormwater drainage shall be by means of a gravity system.
                      Sewer Mains
               48.    All parts of the site shall be connected to Council's existing sewerage reticulation
                      systems and be constructed in accordance with Council's standards and requirements
                      at no cost to Council.
                      Town Water Supply
               49.    All parts of the site shall be connected to Council's existing town water supply and be
                      constructed in accordance with Council's standards and requirements at no cost to
                      Council.
               50.    For Multiple Uses (including Building Format Plans, Group Title Plans, etc)                     the
                      development shall be served by:
                      50.1 A single Body Corporate water meter to measure the total water consumption
                           (including fire hose reels, but excluding fire hydrants and fire sprinkler systems),
                           and
                      50.2 Individual water meters to each tenement capable of being separately rated, and
                      50.3 A fire service (fully testable single detector check with metered bypass), where
                           applicable, for flows to fire hydrants and fire sprinkler systems (excluding fire hose
                           reels).
                      Earthworks
               51.    Filling works required on site shall be carried out in accordance with Section 3.8 of
                      Council's Engineering Design Standards Manual and so as not to cause the additional
                      ponding of water on any adjoining lands or the blockage of, or interference with, any
                      existing overland flowpaths. Detailed site surveys indicating natural surface levels and
                      contours of the adjoining properties must be provided with the application for a
                      Development Permit for Operational Works for Filling and Drainage.
                      This may require the design and construction of drainage pipes and/or an overland flow-
                      path within the development site that caters for drainage from the adjoining sites for a
                      design storm with an Average Recurrence Interval of 1 in 100 years. A private easement
                      for the Drainage of Water encompassing the drainage pipes or overland flow-path will
                      also be required. In this regard a Development Permit for Operational Works shall be
                      obtained.
                      Should evidence be provided to Council indicating that no additional ponding of
                      stormwater will occur on the adjoining properties the requirement for the drainage pipes,
                      overland flow- path and easement shall not apply.
               52.    Earthworks carried out on site shall not affect the structural integrity of any of the existing
                      fences or structures that border the development site. Fences that are affected shall be
                      replaced prior to the Building Certifier issuing the Certificate of Classification. In this
                      regard any fences to be replaced shall be clearly shown on the plans submitted for
                      Operational Works approval.
                      Acid Sulfate Soils
               53.    As the site is located below the 5m AHO, any excavation works consisting of 100m3 or
                      greater and/or any filling works consisting of 500m3 or greater and with an average depth
                      of 0.5m or greater will need to be carried out in accordance with State Planning Policy
                      2/02 Planning and Managing Development Involving Acid Sulfate Soils. In this regard
                      appropriate testing and supporting documentation prepared by a suitably qualified
                      specialist shall be submitted to Council for approval prior to obtaining a Development
                      Permit for Operational Works.




                                                                                                       Page 7 of 18
Document Set ID: 22465906
Version: 7, Version Date: 22/06/2023
Log in to download the original file

Decision Notice - Minor Change - 132007 12 9 [As Published].pdf · 339 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.