2008/383

 

Amended Concurrence Agency Response - IPCC01117608

 

26 Immediately following construction of the works
The dunal areas are to be re-profiled to achieve the natural profile of the system,

* Disturbed areas are to be stabilised agamst wind erosion and rainwater run-off erosion and
revegetated through the re-establishment of the endemic native plants common to the site,

« The revegetated area Is to be fenced off where necessary to prevent pedestrian access across
the area, and

* Riparian vegetation ts to be re-instated adjacent to the access jetty where exashng vegetation is
disturbed and where existing pump infrastructure is removed

27 The drainage of process overflow waters and stormwater assocated vith the sand shefter pumping
station must not cause erosion of the dune or beach system

Site Access

28 Access to the permanent pumping station site shall be along the designated vehicle access track, and
the surrounding dunal vegetation must be maintamed to the satisfaction of the Department of
Environment and Resource Management

Coastal Management

29 The sand shefting activity and/or associated activilies must not cause any long-term maintenance and
management implications

Erosion Prone Areas and Coastal Hazards

30 The Sunshine Coast Regional Council shall be responsible for the removal of the works, if in the opinion
of the Department of Environment and Resource Management, the works causes unacceptable adverse
effects or suffers the effects of erosion to the extent that t becomes a danger to the public

31 Should the sand shefting facility and associated infrastructure be damaged as a result of sea erosion the
Sunshine Coast Regional Council shall be responsible for the removal of all debris from the beach

32 In the event of damage or loss by of the works by sea erosion, the Sunshine Coast Regeonal Council
must submit another applicaton if reconstruction of the works is proposed

33 Awnritten undertaking from the Sunshine Coast Regional Council ts to be recerved by the Department of
Environment and Resource Management agreeing that the works will be considered to be an
expendable structure and that no protection works, other than beach nounshment will be carned out in
the event of an erosion threat

 

Page 6 of 8+ AFOSO109 Department of Environment and Resource Management

Page 11 of 19

 

Used in these records

About this file

File size
562 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Letter - Change to an Existing Approval - Plus Copy sent to DERM & QT (Maritime) [As Published].pdf · 562 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.