Minor Change - MCU17 0568 01 & OPW17 0602 01 [As Published]
Parking
16. A minimum of 30 car spaces, including 1 disabled space must be provided on site, in
accordance with the approved plans.
17. A minimum of 9 bicycle parking spaces, 2 lockers and 1 shower cubicle must be provided on
site.
Electricity and Telecommunication Services
18. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
Landscaping
19. The development site must be landscaped and in accordance with the approved plans.
20. Landscaping must be provided along the frontage of the development at a width of 2m-4.5m.
21. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
22. All landscape works must be maintained generally in accordance with the approved design
for the life of the development.
Noise
23. When requested by Noosa Council, a Noise Impact Assessment Report (NIAR) showing
monitoring and recording of noise levels must be undertaken to investigate any non-
vexatious complaint caused by noise emissions from operations at the premises. Such
monitoring must be undertaken and completed within a reasonable and practicable
timeframe as nominated by council and be performed by a suitably qualified and experienced
person.
24. The NIAR is to be submitted to Council detailing the results of such monitoring and
recommendations for any measures to achieve compliance with limits outlined in Table 1 of
this Decision Notice.
25. Measurement of sound pressure levels (adjusted for tonality and impulse) must be in
accordance with Australian Standard AS1055.1 “Acoustics – Description and measurement
of environmental noise – General procedures”.
26. For the purpose of measuring and certifying relevant noise conditions and reporting (eg.
mechanical plant and equipment, a/c units, motors, refrigeration equipment, compressors,
pumps etc.), a suitably qualified person is either:
a) a Registered Professional Engineer of Queensland, or
b) an environmental consultant with a minimum of 3 years current experience in the field
of acoustics.
Waste
27. Waste storage areas and external storage areas are situated to the rear of the building and
are visually screened by landscaping or fencing.
Page 4 of 15
Document Set ID: 22608628
Version: 4, Version Date: 05/10/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original