Council archive · source document
Decision Notice [As Published] · 132009.363
2009/363
Frontage Works
23. Footpath improvements such as topsoiling, grassing, and tree planting are required to the
Attunga Heights frontage of the site in accordance with Planning Scheme Policy PSP03
Landscaping Plants & Guidelines. Grass shall be couch, free of weeds.
24. A new 1.5m wide concrete path shall be constructed along the Attunga Heights frontage of
the site in accordance with Council’s design standards and to an alignment, which protects
any significant vegetation or any underground services.
Alternatively, in lieu of providing the above path, the applicant shall pay a monetary
contribution of $2,308 (equivalent to the full cost of providing this infrastructure, including
design costs). This amount will be subject to variations in the Consumer Price Index, All
Groups Brisbane from September 2009 until the date of payment. The contribution shall be
paid to Council prior to the commencement of the use.
25. All paths, driveways and parking areas shall be designed and constructed to ensure
pedestrian safety using non-slip materials, to produce an evenly graded surface finish, and
to be in accordance with the Disability Discrimination Act 1992 and Australian Standard
1428.1 Design for Access & Mobility.
26. All redundant vehicular crossings to the site shall be removed and replaced by kerb &
channel, footpath paving and landscaping such as trees and grasses in accordance with
Council’s Standard specifications prior to commencement of the use permitted by this
permit.
Roof Water & Stormwater Drainage
27. Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank
that is installed to ensure water from the rainwater storage system or tank is used for
external uses (such as watering gardens, irrigation, ornamental ponds, water features,
topping-up swimming pools, outdoor cleaning, etc) and for internal (ground floor) use in
washing machine cold taps and toilet cisterns. All rainwater tanks are to be designed and
installed in accordance with the Queensland Development Code (QDC) current at the time of
building approval, and shall be part of the plumbing application for approval. The location
and capacity of the tanks shall be clearly shown on the plans submitted for Building Works
and Operational Works approval and any overflow shall be directed to the road frontage or to
the internal stormwater drainage system.
28. All stormwater drainage (including roof water overflow from the rainwater storage system)
shall be collected and discharged so there is no net increase in stormwater runoff from the
site. Stormwater drainage permitted to drain from the site shall be discharged to Council’s
kerb & channel street drainage system in Attunga Heights. Plans of the drainage design
shall be prepared by a Registered Professional Civil Engineer and submitted to Council prior
to obtaining a Development Permit for Operational Works.
The maximum discharge of stormwater drainage allowable to Council’s kerb & channel
street drainage system at any one location is 25 litres/second.
29. All site stormwater drainage shall be by means of a gravity system.
Water and Sewer
30. Reticulated water supply and sewerage must be provided to the development.
31. An individual water meter shall be located immediately within the property boundary to each
unit of the duplex. Meters must comply with Sunshine Coast Water standards.
32. A pipeline conduit under Attunga Heights shall be provided in accordance with Sunshine
Coast Water Standard Drawing SCW 355.
Page 5 of 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 77 KB (small file)
- File type
No other editions are linked here.