33. Buildings, basements, and other structures must maintain a minimum clearance of 1.0 metre
from the sewer manhole chamber and 1.0 metre from the sewer house connection point.
The existing sewer branch and house connection point must comply with this requirement.
34. All storm water retention systems and gross pollutant traps must maintain a minimum
clearance of 1.5 metres from Council sewerage infrastructure.
35. Any landscape planting within 1.5 metres of Council sewerage infrastructure must be
approved varieties and low growing when mature.
36. Construction works undertaken in the vicinity of Council water supply or sewerage
infrastructure must not adversely affect the integrity of the infrastructure. All costs associated
with repair, replacement or alteration of infrastructure must be met by the applicant.
Earthworks
37. Earthworks required on site shall be carried out in accordance with Council’s Planning
Scheme Policy PSP5 – Engineering Design Standards, so as not to cause the additional
ponding of water on any adjoining lands or the blockage of, or interference with, any natural
watercourses.
38. Earthworks carried out on site shall not affect the structural integrity of any of the existing
fences and/or structures and/or lands that border the development site. Fences that are
affected shall be replaced prior to the Building Certifier issuing the Certificate of
Classification. In this regard any fences to be replaced shall be clearly shown on the plans
submitted for Operational Works approval.
Site Stability
39. A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site,
determine the soil classification, establish whether any measures are required to protect the
stability of adjoining buildings and/or structures and/or land, and make recommendations on
the type of foundation system(s) best suited for the proposed development. The
recommendations of this report shall be incorporated into the design and construction of the
proposed development.
Erosion and Sediment Control
40. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard, plans detailing the methods of controlling erosion and sediment are required
to be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
General
41. A suitably qualified Registered Professional Engineer shall prepare engineering drawings
and specifications for all engineering works that will become Council infrastructure, which
shall be submitted in conjunction with an application for a Development Permit for
Operational Works. In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed
cadastre layout is to be submitted in conjunction with any application for Operational Works.
42. Digital detailed designs including drawings, calculations, specifications etc, shall be
submitted with any application for a Development Permit for Operational Works in respect of
roadworks and stormwater drainage works. The design shall be in accordance with Council’s
Planning Scheme Policy PSP05 – Engineering Design Standards – Roads, Drainage and
Earthworks. To avoid conflict with underground pipes or services, all existing and proposed
services required by the development shall be shown on the plans.
Page 6 of 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 77 KB (small file)
- File type
No other editions are linked here.