Other Change Decision Notice - Council Meeting Decision 131998 981211 5
34. All suitable native trees shall be retained. Details of retained trees shall be submitted
with any application for a Development Permit for Operational Works.
Particular care shall be given not to interfere with the natural ecology around retained
trees likely to cause stress to these trees.
35. The existing vegetation on this site shall be retained except where required to be
removed to enable construction of roads, accesses or pegging of surveyed boundaries.
Particular care shall be taken not to disturb vegetation adjacent to existing creeks and
watercourses.
36. Prior to commencement of any operational works arising out of this permit, security in
the sum of $25,000 must be lodged with Noosa Council, to secure performance of
conditions of this approval relating to works external to this site. The security shall be
in the form of cash or unconditional trading bank guarantee acceptable to the Manager-
Land Development.
The security will be returned upon satisfactory performance of all relevant conditions of
this approval and any other related development permit for operational, less any costs
incurred by Council in ensuring compliance with these conditions of for any additional
inspections incurred for substandard work or works undertaken not in accordance with
the is permit.
37. The requirements of ENERGEX, OPTUS and TELSTRA shall be satisfied in relation to
any existing services which currently traverse the development site. Written
confirmation by the relevant authorities that satisfactory arrangements have been made
to formalise any existing informal services shall be submitted prior to commencement of
the use.
38. All stormwater drainage shall be designed in accordance with the provision of the 1987
Australian Rainfall and Runoff (A.R.R.), Australian Standard AS3500.3.2-1988
‘Stormwater Drainage-Acceptable Solutions’ and Noosa Council Standards. Pipe and
channel drainage systems shall be designed to cater for 10 (ten) year Average
Recurrence Interval design storm for Kabi Road.
39. The water quality of any water originating from and leaving the site shall not vary by
more than 5% form the baseline data for water currently leaving the site measured in
the north eastern area of the development site. Monitoring of water quality in the dams
shall be undertaken monthly during construction and annually during operation.
40. A water quality plan be included in the EMP and once approved, shall be complied with
at all times.
41. Stormwater drainage shall include measures to protect proposed allotments from run-
off from surrounding land. The design shall also address controls for gross pollutants,
nutrient runoff, oil and grease, and silt and sediment.
Underground stormwater systems shall be designed in accordance with Noosa Council’s
Engineering Design Standards, and shall also be connected, where possible to Council’s
existing drainage systems.
An easement of minimum with 4.0 metres shall be granted in favour or Council over any
stormwater pipes that traverse private property.
Designs that concentrate stormwater onto adjoining land shall require separate form
approval from the owner of the land or relevant Government Authority. Such approval
shall be submitted with the design in conjunction with an application for a Development
Permit for Operational Works.
Page 6 of 21
Document Set ID: 23418211
Version: 10, Version Date: 02/01/2025