Client: Hass Holdings ATF The Quasar Trust Location: Taylor Court, Cooroy
Refer to Site Plans in Appendix B for the proposed detention tank location and details.
6.6.1 Detention Tank
The flows up to 39% AEP will be directed to and will be detained within the proposed bioretention
basin and flow greater than the 39% AEP will be detained within the detention tank located at the
lowest point of the site in the south western corner. A diversion chamber prior to the bioretention
basin inlet will divert all flow above a 39% AEP event to the detention tank. Refer to Stormwater
Management Plan in Appendix B. The bioretention basin has a storage component 1.25 m deep
with a surface area of 115 m2, providing a storage volume of 143.75m3. The proposed detention
tank dimensions are approximately 5 m wide x 10 m long x 2 m high providing a maximum
detention volume of 100 m3. The combined detention volume provided between the bioretention
basin and the detention basin is 243.75 m3 with a minimum available depth of about 2.7 m. The
required detention is 171m3 peaking at a depth of 2.12 m in the 1% AEP event. The tank will slow
release via one (1) 325 mm orifice plate and a weir 1.5 m high and 0.45 m wide discharging into a
chamber and connecting to an existing stormwater network on site. Refer to the Stormwater
Management Plan in Appendix B for detail.
Table 11 summarises stormwater flows, storage volumes and stage height for the required
detention tank.
Table 11 - Post-Development Conditions – XP-RAFTS
Stormwater Flows for proposed detention basin
Basin Peak
Basin Inflow Peak Depth
Basin AEP Outflow Storage
(m3/sec) (m3/sec) (m) (m3)
1% 0.724 0.624 2.12 171
Det_tank 10% 0.518 0.349 1.78 122
39% 0.331 0.211 1.45 73
XP-RAFTS modelling predicts that the proposed detention tank will reduce the post-development
peak stormwater flows for all critical storm events. Refer to Table 12 below for detail.
Table 12 - Comparison of Pre & Post-Development (mitigated) Stormwater flows in XP-RAFTS
Existing Mitigated
Catchment AEP Critical Peak Flow Critical Peak Flow
Duration (m3/s) Duration (m3/s)
1% 25 min 0.630 25 min 0.624
Site Area 10% 25 min 0.357 25 min 0.349
39% 60 min 0.219 25 min 0.211
7.0 CONCLUSIONS AND RECOMMENDATIONS
As described in Table 5, the stormwater treatment measures selected for the proposed
development achieve the performance criteria set by the NSC and by the State Planning Policy
(2014). Annual load reductions of TSS, TP and TN between the unmitigated and mitigated MUSIC
model scenarios have been met or exceeded. It is considered that a conservative approach has
been taken as no routing in the drainage links has been adopted.
This site based SWMP has demonstrated that the proposed development, when incorporating the
proposed detention strategies, can be undertaken with non-worsening to the quantity of runoff to
downstream environments.
Covey Associates Pty Ltd 10 Project No: 161968
Consulting Engineers 100415 Rpt Iss A
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.