Council archive · source document
MCU14/0073 Town Planning Report
OPW13/1038
(c) Certificates demonstrating currency of public liability insurance and works
insurance covering the works in line with the planning scheme and
relevant government legislations.
Any changes to the details associated with the supervising RPEQ or Principal
Contractor during construction, must be notified to Council in writing within 5
business days of the change occurring.
4. Any conflict between the development and an existing or proposed service must
be referred to the relevant service authority for determination prior to
commencement of works.
5. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to
assets must be repaired immediately where it creates a hazard to the community.
In circumstances where the damage does not create a hazard to the community,
it must be repaired immediately on completion of the works associated with the
development. A condition report including photographs of the frontage of the site
should be completed and submitted to Council prior to any works commencing.
General
6. All works must be supervised by a Registered Professional Engineer of
Queensland (RPEQ), and they must certify that all works conform to the
Operational Works permit.
7. All works must be constructed in accordance with:
(a) The approved plans and conditions detailed in this Decision Notice
(b) The relevant conditions of the higher order Material Change of Use
approval File: MCU13/0171 and the requirement of any other permits
related to this development.
(c) All relevant Noosa Council Planning Scheme Policies, standard drawings,
standard specifications and guidelines, particularly PSP 5 Engineering
Design Standards – Roads, Drainage and Earthworks.
(d) The latest version of the Healthy Waterways document “Water Sensitive
Urban Design Technical Design Guidelines for South East Queensland”.
(e) Provision of the Work Health and Safety Act and such other legislation as
is applicable to workplace health and safety.
External Roadworks & Road Widening Works
8. All pavement widening or construction of new pavement must join neatly to the
existing pavement so that there are no irregularities in line or level resulting at or
adjacent to the join for the length of the construction. Where necessary the
existing pavement must be brought to a satisfactory standard in accordance with
standard drawing SEQ R-170 and Council’s related engineering standards.
9. The installation and/or modification of any street signs, line marking and Raised
Reflective Pavement Markings (RRPM’s) must be in accordance with the Manual
of Uniform Traffic Control Devices (MUTCD).
Page 3 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
MCU14/0073 Town Planning ReportRelated documentApplication case desk ↗