f. The bioretention system must be formed with batters and not walls and include a
minimum width of 5 metres.
g. Unless directed otherwise by Council, the detention tank will be covered.
h. The plan shall include detailed information in relation to the following aspects of the
design of the bio-retention system:
i. calculations of underdrainage requirements for the bio-retention system;
ii. filter media composition requirements;
iii. a schedule which details how the construction, establishment, certification and
various inspections associated with each treatment measure relate to other civil
works;
iv. Where bioretention basins are used for stormwater quality treatment, the design
must be consistent with all aspects of the Water by Design (2014) Bioretention
Technical Design Guidelines Version 1.1) Healthy Waterways Ltd Brisbane,
including for free draining outlets to and from the bioretention basins, and include
completed copies of the design check and summary contained within that
document to confirm free draining outlets, within reasonable construction
tolerance capabilities are achieved; and
v. presentation of groundwater testing results which demonstrate that all parts of
the treatment measures are located above seasonal high groundwater levels.
A copy of the detailed civil drawings for the bio-retention system must be included as
an appendix to the plan.
i. The plan must include a comprehensive Maintenance Plan for the detention tank and
the bioretention system including the frequency of cleanout, methods of cleanout, and
general maintenance. The plan will include the requirement for regular inspections and
the keeping of records (to be maintained and made available to Council upon request).
The plan is also to stipulate that all necessary improvements are required to be made
immediately upon awareness of any deficiencies in the treatment measure/s. The
detention tank is to be capped and trafficable.
j. The plan shall include details the costs of maintenance (including periodic replacement
of filter media) over the life of the asset.
22. The Maintenance Plan (including costing) must be included in any Community Management
Statement for the site.
23. The Body Corporate for the site must enter into a contract with a suitably qualified
contractor(s) for the maintenance of the stormwater quantity and quality devices and provide
evidence of both the contract and execution of the contract upon request by Council.
24. Prior to the commencement of use, certification is to be submitted to Council from a suitably
qualified stormwater quality specialist to verify that the bioretention works have been
constructed generally in accordance with the approved civil works plans, conditions of
approval and relevant sections of the Construction and Establishment Guidelines: Swales,
Bioretention Systems and Wetlands (SEQ Healthy Waterways Partnership). Council
approval of the constructed stormwater management system is required prior to
commencement of use.
25. Certification is required to include all relevant items noted in Construction and Establishment
Guidelines: Swales, Bioretention Systems and Wetlands (SEQ Healthy Waterways
Partnership) including completed and signed forms.
Acid Sulfate Soils
26. The application for operation works must include an Acid Sulfate Soil and Groundwater
Management Plan for the development prepared by a suitably qualified person and in
Page 48 of 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.