SPECIAL COMMITTEE MEETING REPORT 5 JUNE 2019
accordance with relevant State Government Policy and Guidance material to prevent any
impact to the receiving environment as a result of development within actual or potential acid
sulfate soils, and associated groundwater impacts. Detail design plans provided with the
application for operation works approval must demonstrate how the bedding surrounding
underground pipework will be managed to prevent continual dewatering of groundwaters
along it to the receiving environment, and how any impacts to groundwater from proposed
filling on potential or actual acid sulfate soils will be managed.
Easements
27. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
28. All easements for public or third party infrastructure must be in accordance with the planning
scheme and granted at no cost to the Grantee. Where the Grantee is Council or a service
authority, the easement documentation must be in accordance with the Grantee’s standard
easement terms. Draft easement documentation must be submitted to Council for
endorsement.
29. All works must be kept clear of any existing or proposed easements for public or third party
infrastructure on the subject land, unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
30. All earthworks and associated retaining structures/batters must be undertaken in accordance
with an Operational Works approval, and contained entirely within the subject site unless
written permission from the respective landowner(s) is provided to Council.
31. Earthworks carried out on site must not affect the structural integrity of any of the existing
buildings and/or services and/or structures and/or lands that border the development site.
Damage to Services and Assets
32. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Outdoor Lighting
33. Any outdoor lighting with the potential to affect surrounding residential premises shall be
designed, installed, operated and maintained in accordance with AS4282 “The Control of the
Obtrusive effects of Outdoor Lighting”.
Fencing and Walls
34. Any street fencing to David Low way or Sandpiper Court must be set back an average of 1
metre from the front property boundary. Any fencing on the front boundary must either:
a. not exceed a maximum height of 1.2m
b. be of open construction.
Street Identification
35. The street address of the development must be clearly visible and discernible from the
primary frontage of the site by the provision of a street number and, where appropriate, the
building name.
Page 49 of 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.