v. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Further parked trucks must have engines turned off
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures
c. Works programme identifying key components of the works and their respective
durations
d. Establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues
e. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
For haulage operations involving significant volumes of fill material or excavated material
being transported onto or off the site: details on the location of external fill sites/sources, the
haulage route, type of vehicle to be utilised during filling operations and frequency of usage.
NB any damage to the existing road system as a result of haulage operations shall be fully
repaired at the applicant’s expense.
Stormwater Drainage
16. Stormwater runoff from the development must be disposed of on-site without causing scour
or damage to the subject site or any adjoining property.
17. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken generally in accordance with SCG Consulting’s
Stormwater Management Plan (32288-SW1.1) dated December 2022.
Damage to Services and Assets
18. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Earthworks
19. All earthworks must be undertaken generally in accordance with SCG Consulting’s
Earthworks Plan (32288-OW3.1) dated February 2023. All earthworks and associated
retaining structures/batters, both above and below ground level, both temporary and
permanent, must be contained entirely within the subject site unless written permission from
the respective landowner(s) is provided to Council.
20. Fill material placed over services must not impose any additional surcharge loading on the
service.
21. Excavation must not be carried out within 600mm of any utility infrastructure (to top, sides
and base of services). A retaining wall must be provided to support the soil surrounding utility
infrastructure where proximate to excavation activities.
22. Compaction with a vibrating roller must not be carried out within 600mm of any utility
infrastructure.
23. Other than for accessways, filling must not extend more than 1 metre beyond the footprint of
the approved dwelling when measured from its outer walls.
Page 4 of 8
Document Set ID: 22438820
Version: 3, Version Date: 26/05/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Minor Change - MCU19 0008 02 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 165 KB (small file)
- File type
No other editions are linked here.