Appendix C - Stormwater Management Plan
Attached to the e-mail MCU15/0095 & REC15/0022 Development Application Stormwater Mgmt Plan (2 of 3).
Original PDF page 11, section 1. The text section number identifies this passage in the reader.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnTfA Project Group Pty Ltd Stormwater Management Plan
Development Application
Where:
Qy = peak flow rate (m3/s) for average recurrence interval (ARI) of ‘y’ years
Cy = coefficient of discharge (dimensionless) for ARI of ‘y’ years
A = area of catchment (ha)
tIy = average rainfall intensity (mm/h) for a design duration of ‘t’ hours and an ARI of ‘y’ years.
t = the nominal design storm duration as defined by the time of concentration (tc).
The value of 2.78 x 10-3 (or 1/360) is a conversion factor to suit the units used.
6.2.2 Catchments
The existing catchment boundary has been maintained in the post development scenario. Pre and post-
development catchment information is tabulated in Table 4 below.
Table 4: Catchment details
Pre-development Pre-development Post-development Post-development
Area (Ha) fraction impervious Area (Ha) fraction impervious
0.24 0.0 0.24 0.68
6.2.3 Time of concentration
The time of concentration of the pre-development scenario was calculated using the Friend’s equation for
overland sheet flow and figure 4.09 and 4.10 of the Queensland Urban Drainage Manual (QUDM 2007). The
equation is shown below:
tc = (107.n .L0.333) / S0.2 (QUDM 2007: Equation 4.06)
Where:
tc = overland sheet flow travel time (min)
L = overland sheet flow path length (m)
S = slope of surface (%)
The value ‘107’ is a conversion factor to suit the units used.
The time of concentration for post-development scenarios was determined using the above equation 4.06 with a
minimum of 6 minutes as instructed in the Planning Scheme Policy 5 - Noosa Council. Table 5 below shows the
times of concentration used in the water quantity assessment.
Table 5: Times of concentration for the catchment
Catchment Time of concentration
Pre-development 10.00
Post-development 6.00
6.2.4 Coefficient of Discharge
From Table 4.05.3(a) and 4.05(b)of QUDM, a one hour rainfall intensity for a 1 in 10 year ARI (1I10) of 72.3 mm/hr
and fraction impervious fi of 0.0 has a C10 value for the pre-development catchment of 0.70. The post-
development C10 value is 0.84. Table 6 below shows the Fy factor used to calculate the Cy value for each ARI.
123 Eumundi Road (Cnr Walter Hay Drive), Noosaville QLD 4566 Page 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.