Appendix C - Stormwater Management Plan
Attached to the e-mail MCU15/0095 & REC15/0022 Development Application Stormwater Mgmt Plan (2 of 3).
Original PDF page 12, section 1. The text section number identifies this passage in the reader.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnTfA Project Group Pty Ltd Stormwater Management Plan
Development Application
Table 6: Fy factors for the nominated ARI’s
1 year ARI 2 year ARI 5 year ARI 10 year ARI 20 year ARI 50 year ARI 100 year ARI
(mm/hr) (mm/hr) (mm/hr) (mm/hr) (mm/hr) (mm/hr) (mm/hr)
Fy 0.80 0.85 0.95 1.00 1.05 1.15 1.20
The coefficient of discharge for both pre and post-development catchments is calculated based on equation 4.05
of QUDM and the results shown in Table 7.
Table 7: Coefficients of discharge for pre and post-development scenarios
Coefficient of Discharge 1 year 2 year 5 year 10 year 20 year 50 year 100 year
ARI ARI ARI ARI ARI ARI ARI
Pre-development Catchment 0.56 0.60 0.67 0.70 0.74 0.81 0.84
Post-development Catchment 0.67 0.71 0.80 0.84 0.88 0.97 1.01
6.2.5 Rainfall Intensities
The rainfall intensities for the site were read from an IFD table obtained from the BOM website for the project site
on 25 September 2015. The rainfall intensities for a given time of concentration for the pre and post-development
cases for the nominated ARI’s are shown in Tables 8 and 9.
Table 8: Rainfall intensities for the nominated ARI’s for the pre-development scenario
tc 1 year ARI 2 year ARI 5 year ARI 10 year ARI 20 year ARI 50 year ARI 100 year ARI
(mins) (mm/hr) (mm/hr) (mm/hr) (mm/hr) (mm/hr) (mm/hr) (mm/hr)
10 99.3 126 156 173 196 227 250
Table 9: Rainfall intensities for the nominated ARI’s for the post-development scenario
tc 1 year ARI 2 year ARI 5 year ARI 10 year ARI 20 year ARI 50 year ARI 100 year ARI
(mins) (mm/hr) (mm/hr) (mm/hr) (mm/hr) (mm/hr) (mm/hr) (mm/hr)
6.0 121 154 189 210 238 275 302
6.2.6 Stormwater Design Flows
Table 10 shows the stormwater runoff flows for the pre-development case calculated using the rational method.
Table 10: Stormwater flows generated by the pre-development catchment
Catchment Q1 (l/s) Q2 (l/s) Q5 (l/s) Q10 (l/s) Q20 (l/s) Q50 (l/s) Q100 (l/s)
A (QoutPC) 37.78 50.94 70.48 82.28 97.88 124.16 142.68
Table 11 shows the stormwater runoff flows for the post-development case calculated using the rational method.
123 Eumundi Road (Cnr Walter Hay Drive), Noosaville QLD 4566 Page 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.