GENERAL COMMITTEE MEETING MINUTES                                          14 FEBRUARY 2022


          accordance Noosa Plan PSP 2 – Landscaping and generally in accordance with the
          approved Landscaping Plans and in particular:
          a.    A 1m wide garden along the south side of the ‘public thoroughfare’ easement
                must be provided which includes native species that effectively screen the
                development and grow to a minimum mature height of 4m.
          b.    Plantings along the eastern side of the bio basin must grow to a minimum height
                of 3-4m and provide screening to the car parking area.
          c.    Landscaping works to provide a suitable visual screening buffer between the
                building and the easement with a minimum garden bed width of 800mm.
          d.    The proposed 25 litre pot size feature trees within the front setback (facing
                Doonella Street) must be replaced with 45 litre pot size plants (the SYZ hem,
                CUP ana, ELA ret, ACR imp species)
          e.    The existing street trees in the road reserve may be removed. If removed they
                must be replaced with 4 x ex-ground Delonix regia (poinciana’s) as shown on
                the approved operational works landscape plans.
    56.   All landscape works must be established and maintained in accordance with the
          approved design for the life of the development, and in a manner that ensures healthy,
          sustained and vigorous plant growth. All plant material must be allowed to grow to full
          form and be refurbished when its life expectancy is reached.
    Signage
    57.   Advertising devices must comply with Council’s signage policy.
                           OPERATIONAL WORKS - OPW21/0031
    Approved Plans
    58.   Development undertaken in accordance with this approval must generally comply with
          the approved plans of development. The approved plans are listed in the following table
          unless otherwise amended by these conditions.
           Plan No.         Rev.   Plan/Document Name                          Date
           SD02             12     Ground / Carpark Plan, prepared by          08/07/2021
                                   Archicology P/L
           A6035/21/EW01    F      Earthworks Layout Plan, prepared by Alta    25/05/2021
                                   Engineering
           A6035/21/R01     F      Roadworks Layout Plan, prepared by Alta     25/05/2021
                                   Engineering
           A6035/21/R03     E      Roadworks Doonella Street – Cross           25/05/2021
                                   Sections, prepared by Alta Engineering
           A6035/21/R04     B      Roadworks Setout Plan, prepared by Alta     25/05/2021
                                   Engineering
           A6035/21/R08     A      Roadworks Boundary Cross Sections,          25/05/2021
                                   prepared by Alta Engineering
           A6035/21/D01     E      Stormwater Layout Plan, prepared by Alta    25/05/2021
                                   Engineering
           A6035/21/D02     E      Stormwater Drainage Details, prepared by    25/05/2021
                                   Alta Engineering
           A6035/21/D03     B      Stormwater Drainage Setout Plan, prepared   25/05/2021
                                   by Alta Engineering
           A6035/21/WQ01    E      Stormwater Treatment Catchment Plan,        25/05/2021
                                   prepared by Alta Engineering
           A6035/21/WQ02    E      Stormwater Quality Layout Plan and Notes,   25/05/2021
                                   prepared by Alta Engineering
           A6035/21/WQ03    E      Stormwater Quality Bio Basin Calculations   25/05/2021
                                   and Details, prepared by Alta Engineering


                                                                                  Page 17 of 26
Log in to download the original file

2022-02-14 General Committee Meeting Minutes(PDF, 373KB).pdf · 382 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.