Site Access and Driveways
20. A sealed access driveway must be provided from William Street to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
the conditions of this approval, be generally in accordance with SCG Consulting’s
Operational Works Driveway & Access Plan (00461-OW4.1) and Operational Works
Driveway Details (00461-OW4.2) dated April 2025 and must include in particular:
a. A driveway crossover in accordance with Council standard drawings RS-049 and RS-
050 and any associated addendum.
Car Parking
21. A minimum of 6 car parking spaces must be provided and marked on the site. The works
must be undertaken in accordance with an Operational Works approval and must include in
particular:
a. 1 visitor parking spaces within the total, which are clearly marked for that purpose and
accessible at all times for visitor use;
b. dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities
Stormwater Drainage
22. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with the conditions of this approval
and be generally in accordance with SCG Consulting’s Operational Works Stormwater
Management Plan Basement Level (00461-SW1.1) and Operational Works Stormwater
Management Plan Ground Level (00461-SW1.2) dated April 2025.
Services
23. Reticulated electricity and telecommunication services must be provided to each lot/unit in
accordance with an approval for Operational Works and the standards and requirements of
the relevant service provider.
24. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
25. Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater) which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.
Earthworks and Retaining Walls
26. All earthworks and associated retaining structures/batters, both above and below ground,
both temporary and permanent, must be undertaken in accordance with the conditions of this
approval, be generally in accordance with SCG Consulting’s Operational Works Earthworks
Plan (00461-OW3.1) , Operational Works Earthworks Sections Sheet 1 (00461-OW3.2) and
Operational Works Earthworks Sections Sheet 1 (00461-OW3.2) dated April 2025 and
contained entirely within the subject site unless written permission from the respective
landowner(s) is provided to Council.
27. All retaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
safety fence.
Acid Sulfate Soils
28. All works must be carried out in accordance with updated site-specific Acid Sulfate Soil,
Groundwater and Dewatering Management Plans.
*(Refer to Advisory Note)
Page 5 of 21
Document Set ID: 24062787
Version: 1, Version Date: 27/08/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Planning Report Conditions - Approval (As Publihed)Related documentApplication case desk ↗
Delegated Planning Report Conditions - Approval (As Publihed).pdfRelated documentApplication case desk ↗
About this file
- File size
- 184 KB (small file)
- File type
No other editions are linked here.