b. Carex fascicularis
c. Ficinia nodosa
d. Juncus usitatis
e. Lomandra longifolia
f. Ghania sieberiana
111. Landscape plans for the areas surrounding the bioretention basin filter media footprint
must be arranged to minimise shading to the filter media footprint are. Suitable plants
include the following:
a. Cared appressa
b. Carex fascicularis
c. Ficinia nodosa
d. Juncus usitatis
e. Lomandra longifolia
f. Ghania sieberiana
g. Banksia robur
h. Dianella brevipendunculata
i. Themada triandra
j. Cymbopogan refractus
k. Melaleuca thymifolia
112. Where landscaping/garden beds are proposed adjacent to the bioretention basin, or
where the basin is located adjacent to naturally forested areas, a 900mm deep root
barrier must be installed to the interface between the landscape/garden/forest area and
the bioretention basin to prevent root intrusion to the biobasin infrastructure.
113. Landscaping to the surface of the bioretention basin filter media area must not
commence until 80% of building work within each contributing catchment is complete or
after 3 years, whichever occurs first. An uncompleted works bond of 150% of the value
of the planting to the surface of the bioretention basin filter media area must be provided
to Council prior to the release of the Plan of Survey.
114. Where required, mulch within the batters of bioretention basins must be installed in a
manner that it will not escape into receiving stormwater drainage infrastructure or water
courses.
Bioretention Devices - Education
115. The development shall be provided with approved permanent signage that is deigned in
accordance with Noosa’s Look and Feel document to educate the public on the function
of the bioretention basin. The wording for the signage for each bioretention basin is to
include: “BIORETENTION BASIN - This bioretention basin reduces the pollution of our
waterways by reducing the amount of heavy metals, litter, suspended solids, and
nutrients discharged to Lake Doonella”.
FOLLOWING CONSTRUCTION / PRIOR TO THE ON-MAINTENANCE INSPECTION
Certification
116. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
117. A condition report of the drainage system must be completed for agreement prior to
requesting the works to be accepted On-Maintenance. The condition report is to include
a CCTV inspection of the existing pipe and must include at least 50m upstream and
downstream of all works.
As Constructed Plans and ADAC XML Files (Council)
118. Prior to acceptance of civil works to become Council assets “On Maintenance”,
satisfactory “As-Constructed” records must be submitted to Council. The bundle of “As
Page 27 of 29
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.