Appendix E - Construction Management Plan.pdf
Environmental Management Plan
MANAGEMENT SYSTEMS
Eff. Date:
Rev.: E Pg. 6 of 20
15/07/2020
PROJECT INFORMATION
PROJECT ADDRESS
The project is located on 65-67 Elanda Street, Sunshine Beach
AND LOCALITY
DURATION OF THE
PROJECT
WEEKS: 61 START 09/09/2024 FINISH 07/11/2025
PROJECT The project, has been designed and will be built in accordance with the approved
OVERVIEW plans and specifications.
CONSTRUCTION • Establishment of a construction compound in a designated area (Refer to the Site Map).
OVERVIEW Establishment of a construction compound in a designated area on the street verge.
• Establishment of erosion and sediment controls.
• Construction of any temporary crossovers into the construction compound to permit personnel
and delivery access and aggress from the works area.
• Civil works (including completion of bulk and detailed excavation) to prepare the works area for
building construction.
• Installation of in-ground services.
• Construction of the new building.
• Landscaping.
• Construct of a new roadworks adjacent to the site (kerb and asphalt)
• Concrete driveway
• Site demobilisation
RESPONSIBILITY
On site management of the requirements of the CMP and any associated requirements, remains the
responsibility of the Site Manager and the HSEQ Adviser.
Detailed information regarding the contents of the CMP and associated documentation, Procedures, SOP’s
etc must be provide to subcontractors during Site Induction and prior to their commencement of work on the
project.
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix E - Construction Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.