Appendix E - Construction Management Plan.pdf

of 127
                                           Environmental Management Plan
                                                                      MANAGEMENT SYSTEMS
                                                                               Eff. Date:
                                                                                                   Rev.: E               Pg. 6 of 20
                                                                              15/07/2020




PROJECT INFORMATION

PROJECT ADDRESS
                          The project is located on 65-67 Elanda Street, Sunshine Beach
AND LOCALITY
DURATION OF THE
PROJECT
                              WEEKS: 61         START       09/09/2024                   FINISH        07/11/2025



PROJECT                   The project, has been designed and will be built in accordance with the approved
OVERVIEW                  plans and specifications.


CONSTRUCTION              •     Establishment of a construction compound in a designated area (Refer to the Site Map).
OVERVIEW                        Establishment of a construction compound in a designated area on the street verge.
                          •     Establishment of erosion and sediment controls.
                          •     Construction of any temporary crossovers into the construction compound to permit personnel
                                and delivery access and aggress from the works area.
                          •     Civil works (including completion of bulk and detailed excavation) to prepare the works area for
                                building construction.
                          •     Installation of in-ground services.
                          •     Construction of the new building.
                          •     Landscaping.
                          •     Construct of a new roadworks adjacent to the site (kerb and asphalt)
                          •     Concrete driveway
                          •     Site demobilisation




RESPONSIBILITY


On site management of the requirements of the CMP and any associated requirements, remains the
responsibility of the Site Manager and the HSEQ Adviser.
Detailed information regarding the contents of the CMP and associated documentation, Procedures, SOP’s
etc must be provide to subcontractors during Site Induction and prior to their commencement of work on the
project.

Log in to download the original (Appendix E - Construction Management Plan.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.