Appendix E - Construction Management Plan.pdf
Environmental Management Plan
MANAGEMENT SYSTEMS
Eff. Date:
Rev.: E Pg. 9 of 20
15/07/2020
Category/Activity Aspect Potential Impact/Risks Risk Rating Target Actions and Controls Residual
Risk
C P Initial
Risk
Construction
• Decrease in air and 3 D M • No damage to surrounding • Clearing methods to follow procedures, which L
Activities
Vegetation water quality. ecosystem. incorporate acceptable erosion and stormwater
control management.
clearing • Buildup of sediment in • Sediment and erosion
water systems. does not exceed natural • No burning off-on site.
rates. • Contractors required to remove sediment distributed
• Nil complaints or by vehicles on any road areas (i.e. using sweeper
infringements. trucks).
• Appropriate control measures to be installed to
ensure containment of disturbed areas and
stockpiles.
• Limited disturbance of ground covers to required
excavation areas.
• Stockpiling of excavated material into areas which
have no impact on the eco system.
• Stockpiles vegetated (where practicable) to improve
soil stability.
• Daily inspections and inspections following a major
weather event (i.e. storm, high wind).
• Dust emissions which 2 C M • Compliance with legislative • Develop or implement an Erosion and Sediment L
Erosion and degrade air quality. requirements. Plan which identifies stockpile areas and control
methods to mitigate against erosion and sediment
sediment • Degradation of water • Zero infringement notices creation.
from contamination of or complaints.
watercourses through • Ensure that the handling and placement of
silt and sediment build- excavated material is in accordance with SWMS,
up. Client instructions, EPA requirements etc.
• Install erosion and sediment control devices to
mitigate and manage the impact of excess soils on
surface water quality, air quality, fauna and flora.
• Complete daily inspections of stockpiles, excavated
areas and control methods for erosion and sediment
management.
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix E - Construction Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.