Appendix E - Construction Management Plan.pdf
Environmental Management Plan
MANAGEMENT SYSTEMS
Eff. Date:
Rev.: E Pg. 15 of 20
15/07/2020
DUST The project site is located within an operational business facility and dust minimisation and
MANAGEMENT mitigation methods must be practiced.
Refer to the following for additional information and control methods:
• Access and Egress in this section.
• “CMP Aspects and Impacts Register”.
WATER QUALITY To manage the environmental integrity of the project site, the following protocols apply:
MANAGEMENT
• Before commencing earthworks on any part of the project, materials sufficient to protect
against storms will have been made available on site and the work scheduled to ensure
that, wherever practicable, any permanent or temporary erosion works are in place
before exposing earthworks to storm runoff.
• Where possible, site development and construction will be undertaken in stages to keep
exposed soil areas to a minimum.
• Silt mesh fencing will be placed around low lying project areas and stockpiles to prevent
erosion of stockpiles.
• No untreated wastes will be discharged directly or indirectly to waters.
• Potential pollutants (i.e.: oils, construction materials, rubbish, etc) will be located so as
to minimise the potential for contaminants to enter waterways (i.e.: bunded or housed
well away from drains, drainage channels or waterways).
• The pumping out of collected “muddy” stormwater will not be directly discharged to open
drain or watercourse.
The Site Manager
• Routinely inspect areas identified as being most likely to contribute to sediment
generation
• Inspect sediment barriers during and immediately following major rain events.
• Routinely inspect stockpiles to confirm that their location is not resulting in the
generation and uncontrolled transport of sediment.
Refer to the Erosion and Sediment Control Plan
NOISE The project site is located within an operational business facility and noise minimisation and
MANAGEMENT mitigation methods must be practiced.
Refer to the “CMP Aspects and Impacts Register” for additional information and control
methods.
GENERAL WASTE Disposal of waste must be in accordance with legislative, DA/BA and BBN Constructions
MANAGEMENT WMP requirements.
Containment of waste must be compliant with legislative,) and BBN Constructions
requirements.
MEASURING AND Informal As part of an on-going commitment to environmental management site
MONITORING personnel are required to undertake informal daily, site inspections and
implement corrective actions (i.e. site walk-about).
Weekly On a weekly basis, the Site Manager for the project site will conduct an
environmental check, record the results and file within the site
environmental management filing system.
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix E - Construction Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.