Schedule 12: Energex Requirements
65
Schedule 12: Energex Requirements
Project Name: Noosa Council Project Number: R0506688
The following conditions of supply will apply with the ENERGEX's offer:
Power Quality Conditions
1. The emission limits by the load will be required to comply with the following
Australian/New Zealand Standards:
AS/NZS 61000.3.6:2001- Limits — Assessment of emission limits for
distorting loads in MV and HV power systems.
AS/NZS 61000.3,.7:2001- Limits - Assessment of emission limits for
distorting loads for fluctuating loads in MV and
HV power systems.
IEC /TR 61000-3-14 : Assessment of emission limits for harmonics,
interharmonics, voltage fluctuations and
unbalance for the connection of disturbing
installations to LV power systems
HB 264-2003 — Hand Book in Power Quality
Compatibility levels for Pst and Pit in LV power system are 1.0 and 0.8
respectively (Table 1 of AS/NZS 61000.3.7:2001).
Refer Sections 1.1 and 1.2 for a typical customer emission limits derived
based on user agreed total maximum demand of up to 1.5 MVA. Site specific
limits will be available on request.
2. All motor loads cannot be started simultaneously and the starting current of
the motors must be limited to 2-3 x full rated current by fitting with an
appropriate starters.
3. ENERGEX approval to connect the loads is conditional upon the attached
Network Connection Contract and this agreement to rectify any interference
that may occur in practice. This would require Noosa Council to take
immediate steps to remedy the situation in a short time frame. The cost of any
mitigation measures would be borne solely by the Noosa Council.
4, On the completion of all the electrical load installation, further site
measurement at the PCC/POC will be required to confirm emission limits due
to distorting/ fluctuating loads. Please contact ENERGEX after the
commissioning of the new load(s) for ENERGEX to follow up on
measurements.
5. ENERGEX stress that should the approved electrical loads be exceeded, this
will result in poor voltage regulation to other customers connected to the 11kV
feeder NVL284, Should this occur, ENERGEX will take action to limit the
supply to the Noosa Council.
65See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.