132005.1133.2 Extension to relevant period - Noosa Springs Precinct F
Very large file: it may take a few minutes
The original of this document is very large (11.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
NOOSA COUNCIL IDAS Development Application Decision Notice 6 of 15
35. Turning areas shall be provided at the end of the aisles when required and they shall be line-marked with
chevrons and have the words No Parking" painted on the pavement. A sign shall also be provided to
Indicate that the area is a "Turning Area Only" and that "No Parking is Permitted".
36. All carparking shall be kept, maintained and line-marked in a condition fit for use.
37. All staff carpark spaces shall be dearly defined by line marking each space with the words "Staff Parking
Only" and by sign posting each space with a similar wording.
38. All service driveways shall be designed to comply with AS 2890.1-2004 in particular with regard to
gradients and turning areas required for the light service vehicles.
Vegetation Protection & Preservation
39. Vehicular pavements within the drip zone of any of the existing trees on site to be retained shall be
designed to ensure that the root system water supply is maintained. Pavements shall be constructed so
as not to damage the tree or their root system and in this regard temporary fencing shall be provided
around the trees during construction to help protect them.
Plans shall be submitted to the Council for approval that clearly show the type and extent of the pervious
pavement and/or drainage and the temporary fencing prior to obtaining a Development Permit for
Operational Works.
40. Where retained trees are located in areas proposed to be filled on site (or are located on neighbouring
allotments to the actual site to be filled), there will be a need to prevent fill material from being placed on
the trees root system. To this end the design of the filling works will need to incorporate terracing around
the tree or a similar means of ensuring that the natural ground level around the trees remains generally
the same as existing. These measures shall clearly be shown on the plans submitted for Operational
Works approval and any drainage required to drain these areas shall also be shown on the plans.
Frontage Works
41. Any modifications to the existing road as a result of the proposed driveway access points, including road
widening or realignment, shall be designed and constructed by the applicant.
42. Footpath improvements such as topsoiling, grassing, and tree planting are required to the Leslie Drive
(show as Resort Drive) frontage of the site in accordance with Planning Scheme Policy PSPO3
Landscaping Plants & Guidelines. Grass shall be couch, free of weeds.
43. A new 2.0m wide concrete path connecting the resort to the pathway on the opposite side of the road
shall be constructed as shown on in accordance with Council's design standards and to an alignment that
protects any significant vegetation or any underground services. A pram ramp shall be installed where
the pathway crosses the kerb line.
44. All paths, pram ramps, driveways and parking areas shall be designed and constructed to ensure
pedestrian safety using non-slip materials, to produce an evenly graded surface finish, and to be in
accordance with the Disability Discrimination Act 1992 and Australian Standard 1428.1 Design for Access
& Mobility.
Undergrounding Power
45. Any connection to the site for power and telecommunications will be underground.
Roof Water & Stormwater Drainage
46. Roof water runoff from any new building should be directed to a rainwater storage systems or tanks that
provide minimum storage of 400,000 litres. Storages and/or tanks shall be installed to ensure water from
the tanks/storages is used for external uses (such as watering gardens, irrigation, ornamental ponds,
water features; topping-up swimming pools, outdoor cleaning, etc) and for use in flushing of toilets internal
to the building. All rainwater tanks are to be designed and installed in accordance with the Queensland
Development Code (QDC), Part 25 - Rainwater Tanks, and shall be part of the plumbing application in
conjunction with the building approval. The location and capacity of the tanks shall be dearly shown on
the plans submitted for Operational Works approval and any overflow shall be directed to the road
frontage/the stormwater drainage system/etc located on Leslie Drive.
47. All stormwater drainage (including roof water overflow from the rainwater storage system) shall be
collected and discharged so there is no net increase in stormwater runoff from the site. Stormwater
drainage permitted to drain from the site shall be discharged generally in accordance with Tate
Professional Engineers Drawing Number C1732105/F/P04 revision H dated 07/06/07.
MG j:ldatawrkstwrkcachel1478732105-1133 ndn.doc
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.