Council archive · source document
Decision Notice - Change to an Existing Approval - 010.2007.00001586.002 [As Published] · 132007.1586.02
2007/1586
4 ASSESSMENT MANAGER CONDITIONS
General
1. Development undertaken in accordance with this approval must generally comply with the approved
plans of development. The approved plans are titled Demolition Plan, Site/Ground Floor Plan, Site/First
Floor Plan and Elevations prepared by De Nova Group Pty Ltd and dated June 2007 and as may be
amended by these conditions.
2. The development must be undertaken and operated in a manner that causes no detrimental effect upon
the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other
emissions.
3. The building height shall not exceed 8.0 metres above natural ground level.
4. A minimum of 20% of the site shall be retained as soft landscaping.
5. The area within 4.5 metres of the revetment wall shall be developed in accordance with the following
requirements:
5.1. A minimum of 25% of the area is planted with shrubs; and
5.2. A maximum of 25% of the area is under hard pavement and the balance is to be turf or ground
covers; and
5.3. No tree species with a mature height of over 3m are to be planted; and
5.4. No shrubs are to be planted within 1m of the revetment wall; and
5.5. The ground surface within the first metre from the revetment wall is turf, ground cover or hard
pavement.
3
6. As the site is located below the 5m AHD, any excavation works consisting of 100m or greater and/or
3
any filling works consisting of 500m or greater and with an average depth of 0.5m or greater will need to
be carried out in accordance with the recommendations found in the Soil Surveys report entitled Acid
Sulfate Investigation & Management - Project No. 307-2624 August 2007.
7. As the proposed works are carried out adjacent to Noosa Waters waterways reserve, any person acting
on this permit shall be responsible to prevent erosion and sediment entering the waterways. Site control
measures such as silt fencing and a controlled disposal of waste may be required. The applicant shall be
responsible to rectify any environmental or pollution adverse impacts on the waterways reserve that
might have been caused by the proposed works.
8. The applicant shall be responsible to repair any damage to the revetment wall or its stability where it is
caused due to the proposed works.
9. Upon completion of the proposed works, a Registered Professional Engineer of Queensland shall certify
that no damage has been caused to the existing revetment wall due to the works.
10. The Applicant shall be responsible for the full cost of repairs to road pavement, footpath, kerb and gutter,
or other Council property and facilities damaged as a result of construction of the proposed works.
11. All electrical fixtures, outlets and switches within the flood storage area shall be placed above the 1 in
100 years flood level (RL 2.0m AHD) or be flood proofed and be certified by a licensed electrician.
12. All hot water systems installed shall be either solar systems; electric heat pump systems; or gas systems
(LPG or natural).
13. A rainwater storage tank with a minimum capacity of 5000 litres shall be provided on site to service the
detached house. The tank is to be installed to ensure water from the tank can be used both:
13.1. for external use such as watering gardens, irrigation, ornamental ponds or water features, topping
up swimming pools, outdoor cleaning; and
13.2. for use in flushing of toilets internal to the building.
Page 2 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval - 010.2007.00001586.002 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 60 KB (small file)
- File type
No other editions are linked here.