ORDINARY MEETING AGENDA                                                  20 NOVEMBER 2014


        Earthworks
        1920. Any earthworks required on site shall be carried out in accordance with
              Council’s Planning Scheme Policy PSP5 – Engineering Design Standards –
              Roads, Drainage and Earthworks and must be undertaken in accordance with a
              Development Permit for Operational Works.
        210. Earthworks carried out on site shall not affect the structural integrity of any of
             the adjoining properties, existing fences or structures that border the
             development site. Fences that are affected shall be replaced prior to the
             Building Certifier issuing the Certificate of Classification. In this regard any
             fences to be replaced shall be clearly shown on the plans submitted for
             Operational Works approval.
        UNITYWATER
        The following Unitywater conditions are applied in accordance with the South East
        Queensland (Distribution and Retail) Restructuring Act 2009 and Unitywater’s Interim
        Connections Policy. The conditions below form part of a water connection aspect
        which are taken to be a water approval for a staged connection. Any future
        applications must be made to Unitywater under South East Queensland (Distribution
        and Retail) Restructuring Act 2009. Unitywater can be contacted as follows:
        Phone: 1300 0 Unity (1300 086 489)
        Email: [email protected]
        Web: www.unitywater.com
        Water & Sewerage
        221. Reticulated water supply and sewerage must be provided to the development.
        232. Construction activities must not impede the access of Unitywater or Fire
             Brigade personnel to vital infrastructure (eg. valves, fire hydrants and sewer
             access chambers).
        243. The fire-fighting demand on Unitywater’s water supply system from the
             development must not exceed 30 litres per second.
        254. A single Unitywater installed primary water meter must be provided immediately
             inside the property boundary. Meters must be Unitywater approved, installed in
             accordance with Unitywater requirements and remain accessible at all times for
             reading and maintenance purposes.
        265. Water meters must be located on alternative boundaries to electrical pillars.
        276. Buildings, basements and other structures must maintain a minimum clearance
             of 1.5 meters from Unitywater sewer mains, and 1.0 meter from a sewer
             manhole chamber or sewer inspection opening.
        287. Easements of between 3 and 10 metres must be provided over all Unitywater
             sewers located within property boundaries in accordance with the SEQ
             standards. Easements shall be centred over the pipe. Easement terms shall be
             the most current registered dealing held by the Department of Natural
             Resources & Mines and shall not be altered or amended.
        298. Storm water retention systems and gross pollutant traps must maintain a
             minimum clearance of 1.5 meters from Unitywater water supply and sewerage
             infrastructure.
        2930. Tree plantings must maintain a minimum horizontal clearance of 1.0 metre from
              Unitywater water mains and 1.5 metres from Unitywater sewerage mains.
              Landscaping plants within these clearances must be low growing when mature,
              and suitable approved varieties.


                                                                                Page 17 of 24
Log in to download the original file

2014-11-20 Ordinary Meeting Agenda(PDF, 328KB).pdf · 336 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.