                                                                                       2008/831



19.   The Consulting Engineers for the project shall be currently Registered Professional Engineers
      of Queensland (RPEQ).          The consulting engineers are responsible for arranging all
      inspections with Council’s Construction Technical Officer or nominated staff. Council’s
      Construction Technical Officer shall provide an inspection form for signing off by the Engineer
      at appropriate stages of construction, during on-site meetings. Council’s Construction
      Technical Officer will also sign the form at each stage when requested conditions have been
      satisfied. The works will be accepted “On maintenance” after this form has been signed by
      Council’s Construction Technical Officer, together with a letter from the Engineer requesting
      that the works go “On maintenance”.
20.   Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
      project. (This person will be the contact for the project).
21.   Council standards shall apply to these works unless otherwise modified herein.
22.   The person acting on this permit shall ensure that its consultants and contractors take all
      reasonable care during the construction of the engineering works to ensure that Council
      property, road pavements or facilities (such as underground drainage, water supply,
      sewerage, footpaths, kerbing, landscaping, street furniture, etc.) are protected against any
      damage or interference whatsoever.
      If any Council property or facilities should be damaged by the Applicant or any of its
      Consultants or Contractors through any cause whatsoever in the course of, directly or
      indirectly, carrying out the engineering works, the Applicant and/or its Contractors shall
      forthwith notify the Manager Land Development and shall forthwith rectify the damage to that
      property or facility at its cost and to the satisfaction of the Manager Land Development.
      All rectification works are to be completed prior to the commencement of the use or,
      alternatively, the Applicant may request Council to carry out the rectification work at the
      Applicant’s cost, such cost being paid by the Applicant to Council prior to the commencement
      of the use.
      In the case of any emergency, Council shall be entitled to rectify such damage at the cost of
      the Applicant, such cost being paid prior to the commencement of the use.
23.   The development of the site shall be carried out in such a manner as to prevent dust and/or
      sand nuisance to residents and/or tenants in the vicinity of the development.
24.   Construction work and other associated activities are permitted only during the hours
      of 7.00 am and 6.00 pm Monday to Saturday. No work is permitted on Sundays or public
      holidays, except where extended hours are approved by the Manager, Land Development, or
      his nominee.
25.   Safe pedestrian access along David Low Way in the vicinity of the development shall be
      maintained at all times. If footpath / road closures are necessary to carry out construction
      works, Council’s Construction Technical Officer (phone 0410 512 505) must be notified prior to
      the proposed closure.
26.   Sediment and erosion control measures must be in place prior to works commencing. If such
      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
      fines can be issued if sediments from the site are found to enter or have the potential to enter
      Council’s stormwater system or natural waterways. Although the sediment and erosion control
      measures have been approved on Barlow Gregg’s drawing M3087 – C02 B, Council’s
      Manager, Land Development, may request further controls to be installed should approved
      measures be inefficient.
27.   The owner of the subject property shall inspect the gross pollutant traps on a weekly basis,
      after each storm event and in accordance with the manufacturer’s specifications. The owner
      shall also enter into an ongoing maintenance contract with a Registered Contractor to clean
      and maintain the gross pollutant traps at regular three monthly intervals and on an “On Call”
      basis in the case of an emergency.
                                                                                    Page 4 of 11

Used in these records

About this file

File size
72 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2008.00000831.001 [As Published].pdf · 72 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.