                                                                                        2008/831



      The management and maintenance of the gross pollutant traps shall be included in the
      Community Management Scheme for the completed development.
28.   All stormwater drainage lines, including private drainage lines or as otherwise approved by
      Council’s Manager of Land Development shall be inspected by closed circuit television
      (CCTV) at the completion of all works and immediately prior to acceptance of ‘On
      Maintenance’. Council’s Construction Technical Officer shall be advised of the timing of this
      inspection.
      A report of the CCTV inspection, including photographic records (which includes photos &
      video recordings burnt onto a CD) of the inspection shall be submitted to the Council for
      approval. Any defects or substandard works shall be recorded and accurately illustrated on
      the drainage plan showing the location of the defect(s).

      Substandard work will not be accepted ‘On Maintenance’ and must be rectified at the
      applicants expense with a further CCTV inspection arranged once the rectification works have
      been completed.
      To this extent all CCTV inspections, including any additional inspections necessary following
      defect identification and rectification, shall be entirely at the applicant’s expense. Any costs
      incurred by Council in reviewing the CCTV inspection results shall also be borne by the
      applicant.
29.   Prior to acceptance of civil works to become Council assets "On Maintenance", the lodgement
      of satisfactory “As Constructed” records shall be submitted to Council.
      As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
      (RPEQ) for design intent, and a Licensed Surveyor shall certify the cadastre and the location,
      level and type of all services and structures. All of which shall be submitted to Council for
      checking and for Council’s records.
      The data must fully detail levels for all engineering works including but not limited to drainage
      structures, finished ground levels and pavement surface levels. The data shall be submitted in
      the Asset Design and As Constructed (ADAC) digital format. Guidelines on the use of ADAC
      are available at www.adac.com.au and Council’s “Noosa Planning Scheme Policy 5 –
      Engineering Design Standards – Roads, Drainage and Earthworks”.
      Approval of works shall not be granted until all As Constructed information has been supplied
      and accepted by Council.
30.   A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will
      be imposed on construction works during the maintenance period, which is a minimum period
      of 12 months duration. Such bond must be lodged by, and shall only be accepted from the
      Developer for the works.
31.   The works to become Council assets will not be accepted "On Maintenance" until the
      landscaping is completed.
32.   Notwithstanding that Council has checked the plans with due care, where it is found during
      construction that variations from Council's standards exist, then Council standards shall apply.
Water and Sewer
33.   The names of any proposed contractors for works are to be submitted in writing, together with
      copies of current Public Liability and Workers Compensation Insurances together with
      certificates of currency for those policies, for consideration by the Assessment Manager seven
      (7)     days     prior   to     pre-start    meetings     and     commencement      of    works.
      A separate letter will then be issued approving the contractor (or otherwise) for the works. No
      other contractor or subcontractor shall be engaged to carry out the works or any part of the
      works without the written approval of the Assessment Manager.


                                                                                     Page 5 of 11

Used in these records

About this file

File size
72 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2008.00000831.001 [As Published].pdf · 72 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.