Town Planning Assessment Report
Attached to the e-mail Operational Works Application - DA Form 1 - Town Planning Report - Global Stability Assessment Report - Earthworks Compaction Report - Erosion and Sediment Control Plan - 36 Tunba Court Cooroy Mountain.
Vegetative waste AO5.1 AO5.1 - 5.4 - Not Applicable
PO5 Cleared vegetation is transported off- The earthworks did not require
Vegetation cleared from a site for disposal in an approved green clearing of vegetation.
development site is disposed of in waste disposal facility.
an environmentally responsible
manner. AO5.2
Cleared vegetation is mulched on-
site and reused for landscaping of the
finished development.
AO5.3
Cleared vegetation is disposed of for
the purpose of firewood.
AO5.4
Disposal of vegetative waste by
burning off is avoided.
Managing contamination risk AO6.1 AO6.1 - Complies
PO6 Fill material is solid clean earth, free of All material was contained within
Materials used as fill are suitable for putrescible or refuse the development footprint.
development and future use of the material, vegetation, acid sulfate
land and filling or excavation works soils, building or construction material
do not result in the contamination of or other material or contaminants.
land.
AO6.2 AO6.2 - Complies
The site is not on the contaminated The site is not on the contaminated
land register. land register.
Haulage activity and amenity No acceptable outcome provided PO7 - Not Applicable
PO7 No material will be transported to
Haulage of material to and from and from the site.
a site ensures—
a) minimal disturbance to
neighbouring properties and
properties along the haulage
route; and
b) Council’s road infrastructure
including pavements is not
adversely affected.
Extent of earthworks AO8 AO8 - Complies
PO8 All earthworks, including cut and fill All material will be contained within
The layout of the development batters, retaining walls and the like are the development footprint.
provides adequate, clearly defined contained within the subject site.
and easily accessible—
a) on-site vehicle parking and
manoeuvring areas; and
b) loading and manoeuvring areas
for delivery and service
vehicles.
Sloping sites AO9 PO9 - Performance Outcome
PO9 Cut or fill is less than 1.5 metres in The cut and fill depths exceeds
On sloping sites development depth relative to the natural ground 1.5m in height as detailed on the
follows the natural landform level. proposal plans. The cut and fill
Page 10 of 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.