26 July 2012
Department of
Transport and Main Roads
Vasard Marine
169 First Avenue
Bribie Island Qld 4507
Dear Sir
Tidal Works -
Request for comments
Pontoon -
J Alizzi, 10 Noosa Parade,Noosa Heads (Lot4 RP183112)
Thank you for your letter 27 June 2012 about your proposal to construct a pontoon at the location
mentioned above.
As a concurrence agency, Maritime Safety Queensland has no objection to the proposal provided the
following navigation and marine safety conditions are complied with.
1. The contractor must build the pontoon according to Vasard Marine Pty Ltd, drawing SP-404/1,
attached to your letter dated 27 June 2012.
2. No part of the structure or any ship berthed at this structure is to come closer than 1.5metres from
the side boundaries of the allocated water space as shown on the submitted water allocation plan.
3. In the absence of a designated quayline, the structure and any part thereof must not extend beyond
that ofneighbouring approved structures.
4. The applicant or his agent is responsible for the removal of any existing structure above or below
the waterline, and must contain and remove any debris. Any pile that needs to be removed must
be totally extracted.
5. The ship moored at this pontoon must follow the most direct course from this structure to open
waters and a similar direct course when returning to this pontoon.
Department of Transport and Main Roads Our ref 215/01638 P14840-MOM P14872-MOM
Maritime Safety Queensland Your ref
Marine Operations (Brisbane) Enquiries Geoff Prendergast
MacArthur Avenue East Telephone +61 7 38603504
Pinkenba Queensland 4008 Facsimile +61 738603571
Website www.msq.qld.gov.au
Email [email protected]
[OCR of page images]
Queensland
Government
26 July 2012
Department of
. Transport and Main Roads
Vasard Marine
169 First Avenue
Bribie Island Qid 4507
Dear Sir
Tidal Works — Request for comments
Pontoon — J Alizzi, 10 Noosa Parade, Noosa Heads (Lot 4 RP183112)
Thank you for your letter 27 June 2012 about your proposal to construct a pontoon at the location
mentioned above.
As a concurrence agency, Maritime Safety Queensland has no objection to the proposal provided the
following navigation and marine safety conditions are complied with.
1. The contractor must build the pontoon according to Vasard Marine Pty Ltd, drawing SP-404/1,
attached to your letter dated 27 June 2012.
2. No part of the structure or any ship berthed at this structure is to come closer than 1.5metres from
the side boundaries of the allocated water space as shown on the submitted water allocation plan.
3. Inthe absence of a designated quayline, the structure and any part thereof must not extend beyond
that of neighbouring approved structures.
4. The applicant or his agent is responsible for the removal of any existing structure above or below
the waterline, and must contain and remove any debris. Any pile that needs to be removed must
be totally extracted.
5. The ship moored at this pontoon must follow the most direct course from this structure to open
waters and a similar direct course when returning to this pontoon.
Department of Transport and Main Roads Our ref 215/01638 P14840-MOM P14872-MOM
Maritime Safety Queensland Your ref
Marine Operations (Brisbane) Enquiries Geoff Prendergast
MacArthur Avenue East Telephone +61 7 3860 3504
Pinkenba Queensland 4008 ‘ Facsimile +61 7 3860 3571
Website www.msgq.qid.gov.au
Email [email protected]
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Development Application part 2 of 2.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.