       A maintenance plan for the treatment devices shall be complied with for the
       duration of the approved uses,
       A Development Permit for Building Works shall not be granted until a
       Development Permit for Operational Works has been issued in regard to the
       drainage scheme.
47. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains

48, All parts of the site shall be connected to Council's existing sewerage reticulation
     systems and be constructed in accordance with Council's standards and requirements
       at no cost to Council.

Town Water Supply
49. All paris of the site shall be connected to Council's existing town water supply and be
      constructed in accordance with Council's standards and requirements at no cost to
       Council.

50. For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the
     development shall be served by:
       50.1. A single Body Corporate water meter to measure the total water consumption
             (including fire hose reels, but excluding fire hydrants and fire sprinkler systems),
               and

       50.2. Individual water meters to each tenement capable of being separately rated, and
       50.3. A fire service (fully testable single detector check with metered bypass), where
             applicable, for flows to fire hydrants and fire sprinkler systems (excluding fire
             hose reels).
Earthworks

51 . Filling works required on site shall be carried out in accordance with Section 3.8 of
      Council's Engineering Design Standards Manual and so as not to cause the additional
      ponding of water on any adjoining lands or the blockage of, or interference with, any
      existing overland flowpaths. Detailed site surveys indicating natural surface levels and
      contours of the adjoining properties must be provided with the application for a
      Development Permit for Operational Works for Filling and Drainage.
       This may require the design and construction of drainage pipes and/or an
       overland flow"path within the development site that caters for drainage from the
       adjoining sites for a design storm with an Average Recurrence Interval of I in
       I00 years' A private easement for the Drainage of Water encompassing the
       drainage pipes or overland flow-path will also be required, In this regard a
       Development Permit for Operational Works shall be obtained.
       Should evidence be provided to Council indicating that no additional ponding of
       stormwater will occur on the adjoining properties the requirement for the
       drainage pipes, overland flow-path and easement shall not apply.




Legal/4754/127_I

Used in these records

About this file

File size
5.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 3 - Infrastructure Agreement.pdf · 5.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.