Log in to see the plans as drawnOperational Management and Maintenance Manual for Stormwater Quality Improvement Devices CC-3668
2. RAINWATER REUSE TANKS
2.1. Background
Rainwater reuse tanks provide benefits in terms of both water conservation and stormwater
management. Reuse of harvested roofwater reduces the volume of stormwater runoff entering
watercourses and associated stormwater pollutant loads.
2.2. Inspection and Maintenance
Table 2.1 outlines the various inspection and maintenance tasks required for each aspect of the
rainwater resuse tanks. The inspection and maintenance tasks outlined in Table 2.1 are consistent with
those outlined in Rainwater Tanks (DERM, 2008) and should be implemented to ensure the
effectiveness of the rainwater reuse tanks. Inspection and maintenance of rainwater reuse tanks is the
responsibility of each individual home owner.
Table 2.1 – Inspection and Maintenance Plan for Rainwater Reuse Tanks
Inspection and
Aspect Maintenance Inspection and Maintenance Activities
Frequency
First Flush Device 3 monthly Check that it is working effectively and clean if
necessary.
Gutters 6 monthly Regularly inspect the gutter and clean if necessary.
Keeping gutters as clean as possible will enable them
to drain freely and avoid contaminants entering the
tank.
Roof 6 monthly Check for accumulated debris including leaf and other
plant material. Remove all debris and prune
overhanging branches.
Tank inlets, insect- 6 monthly If necessary these should be cleaned and repaired.
proofing and leaf
filters
Tank and tank roof 6 monthly Check structural integrity of the tank, including roof
and access cover. Any holes or gaps should be
repaired.
Pipework 6 monthly Check for structural integrity and that all pipework
connections remain secure.
Internal inspection 6 monthly Check for evidence of access by animals, birds or
insects, including the presence of mosquito larvae. If
present, identify and close access points.
2 to 3 yearly Check inside the tank for accumulated sediment. If
sludge is covering the bottom of the tank, siphon it
out or completely empty the tank.
2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.