PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 9 JULY 2019
40. All staff carpark spaces shall be clearly defined by line marking each space with
the words "Staff Parking Only" and by sign posting each space with a similar
wording.
Pathway Lighting
41. The existing pathway between the two existing lots shall have lighting installed
from Goodchap Street to the rear boundary of Lot 4. This lighting shall have a high
energy efficient rating to the reasonable satisfaction of Council and be designed to
meet appropriate safety standards and not to adversely impact residences in the
area.
Vegetation Protection & Preservation
42. Vehicular pavements within the drip zone of any of the existing trees on site to be
retained shall be designed as a pervious pavement (such as grass paving cells or
similar), as this will allow water that falls on this surface to penetrate to the trees
root system. The pavement shall be constructed so as not to damage the tree or
their root system and in this regard temporary fencing shall be provided around the
trees during construction to help protect them.
Plans shall be submitted to the Council for approval that clearly show the type and
extent of the pervious pavement and the temporary fencing prior to obtaining a
Development Permit for Operational Works.
Frontage Works
43. Tree planting is required to the Goodchap Street frontage of Proposed Lot 5 in
accordance with Planning Scheme Policy PSP03 Landscaping Plants &
Guidelines.
Roof Water & Stormwater Drainage
44. Stage A - Roof runoff from any new building shall be directed to a rainwater storage
system or tank (minimum storage the greater of 5000 litres or 15 litres/m2 of roof
area) that is installed to ensure water from the tank is used for external uses (such
as watering gardens, irrigation, ornamental ponds, water features, outdoor
cleaning, etc) and for use in flushing of toilets internal to the building. All rainwater
tanks are to be designed and installed in accordance with the Queensland
Development Code (QDC), Part 25 - Rainwater Tanks, and shall be part of the
plumbing application in conjunction with the building approval. The location and
capacity of the tanks shall be clearly shown on the plans submitted for Building
Works / Operational Works approval and any overflow shall be directed to an
approved discharge point.
All stages:
45. All stormwater drainage (including roof water overflow from the rainwater storage
system) must be collected and discharged so there is no net increase in stormwater
runoff from the site.
46. A Stormwater Management Plan must be submitted to Council in conjunction with
an operational works application to demonstrate how water quality and quantity
objectives are to be met as follows:
No increase in peak flow runoff from the site up to and including a one in 100
year ARI.
80% reduction in total suspended solids;
60% reduction in total Phosphorus
45% reduction in total Nitrogen compared to an unmitigated development
scenario.
Page 17 of 128
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.