Skip to the record
For the highest quality transcripts.

Original source · versioned page text

2019-07-09 Planning & Environment Committee Agenda

of 128

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (13.2 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA                                   9 JULY 2019


          This Management Plan must set the objectives and include a plan indicating
          location and sizing of the devices prosed. The operational works application shall
          be in accordance with this plan and buildings must be modified if required to
          accommodate the treatment infrastructure wholly within the allotment.
          A maintenance plan for the treatment devices must be complied with for the
          duration of the approved uses.
          A Development Permit for Building Works must not be granted until a Development
          Permit for Operational Works has been issued in regard to the drainage scheme.
    47.   All site stormwater drainage shall be by means of a gravity system.
    Sewer Mains
    48.   All parts of the site shall be connected to Council's existing sewerage reticulation
          systems and be constructed in accordance with Council's standards and
          requirements at no cost to Council.
    Town Water Supply
    49.   All parts of the site shall be connected to Council's existing town water supply and
          be constructed in accordance with Council's standards and requirements at no cost
          to Council.
    50.   For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the
          development shall be served by:
         50.1 A single Body Corporate water meter to measure the total water
              consumption (including fire hose reels, but excluding fire hydrants and fire
              sprinkler systems), and
         50.2 Individual water meters to each tenement capable of being separately
              rated, and
         50.3 A fire service (fully testable single detector check with metered bypass),
              where applicable, for flows to fire hydrants and fire sprinkler systems
              (excluding fire hose reels).
    Earthworks
    51.   Filling works required on site shall be carried out in accordance with Section 3.8 of
          Council's Engineering Design Standards Manual and so as not to cause the
          additional ponding of water on any adjoining lands or the blockage of, or
          interference with, any existing overland flowpaths. Detailed site surveys indicating
          natural surface levels and contours of the adjoining properties must be provided
          with the application for a Development Permit for Operational Works for Filling and
          Drainage.
          This may require the design and construction of drainage pipes and/or an overland
          flow- path within the development site that caters for drainage from the adjoining
          sites for a design storm with an Average Recurrence Interval of 1 in 100 years. A
          private easement for the Drainage of Water encompassing the drainage pipes or
          overland flow-path will also be required. In this regard a Development Permit for
          Operational Works shall be obtained.
          Should evidence be provided to Council indicating that no additional ponding of
          stormwater will occur on the adjoining properties the requirement for the drainage
          pipes, overland flow- path and easement shall not apply.
    52.   Earthworks carried out on site shall not affect the structural integrity of any of the
          existing fences or structures that border the development site. Fences that are
          affected shall be replaced prior to the Building Certifier issuing the Certificate of
          Classification. In this regard any fences to be replaced shall be clearly shown on
          the plans submitted for Operational Works approval.

                                                                                Page 18 of 128
Log in to download the original file

2019-07-09 Planning & Environment Committee Agenda(PDF, 13MB).pdf · 13.2 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.