PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 9 JULY 2019
This Management Plan must set the objectives and include a plan indicating
location and sizing of the devices prosed. The operational works application shall
be in accordance with this plan and buildings must be modified if required to
accommodate the treatment infrastructure wholly within the allotment.
A maintenance plan for the treatment devices must be complied with for the
duration of the approved uses.
A Development Permit for Building Works must not be granted until a Development
Permit for Operational Works has been issued in regard to the drainage scheme.
47. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
48. All parts of the site shall be connected to Council's existing sewerage reticulation
systems and be constructed in accordance with Council's standards and
requirements at no cost to Council.
Town Water Supply
49. All parts of the site shall be connected to Council's existing town water supply and
be constructed in accordance with Council's standards and requirements at no cost
to Council.
50. For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the
development shall be served by:
50.1 A single Body Corporate water meter to measure the total water
consumption (including fire hose reels, but excluding fire hydrants and fire
sprinkler systems), and
50.2 Individual water meters to each tenement capable of being separately
rated, and
50.3 A fire service (fully testable single detector check with metered bypass),
where applicable, for flows to fire hydrants and fire sprinkler systems
(excluding fire hose reels).
Earthworks
51. Filling works required on site shall be carried out in accordance with Section 3.8 of
Council's Engineering Design Standards Manual and so as not to cause the
additional ponding of water on any adjoining lands or the blockage of, or
interference with, any existing overland flowpaths. Detailed site surveys indicating
natural surface levels and contours of the adjoining properties must be provided
with the application for a Development Permit for Operational Works for Filling and
Drainage.
This may require the design and construction of drainage pipes and/or an overland
flow- path within the development site that caters for drainage from the adjoining
sites for a design storm with an Average Recurrence Interval of 1 in 100 years. A
private easement for the Drainage of Water encompassing the drainage pipes or
overland flow-path will also be required. In this regard a Development Permit for
Operational Works shall be obtained.
Should evidence be provided to Council indicating that no additional ponding of
stormwater will occur on the adjoining properties the requirement for the drainage
pipes, overland flow- path and easement shall not apply.
52. Earthworks carried out on site shall not affect the structural integrity of any of the
existing fences or structures that border the development site. Fences that are
affected shall be replaced prior to the Building Certifier issuing the Certificate of
Classification. In this regard any fences to be replaced shall be clearly shown on
the plans submitted for Operational Works approval.
Page 18 of 128
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.