2019-07-09 Planning & Environment Committee Agenda

of 128

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (13.2 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA                                      9 JULY 2019


     67.   Prior to the issue of any Building Approval and commencement of the construction
           of Stage D (refer Site Plan DA 01F) in the northwest corner of the site, an
           Operational Works approval shall be obtained to address necessary vehicle
           access arrangements and additional vehicle movements to, and within the site.
B.   Include the following new conditions:
     68.   Staging of the development is to be in accordance with Site Plan DA 01F (as
           annotated by Council).
     Access for Stage D
     69.   Vehicular access arrangements must be varied to allow for an alternative access
           arrangement for northern vehicle access to the site from Goodchap Street. The
           alternative access arrangement shall be generally in accordance with Drawing
           No. 17548-C003 Rev B prepared by TOD Noosa dated 14 September 2018. The
           works shall include but not be limited to:-
           i.     The linemarking necessary to provide the right turn lane and
                  associated medians,
           ii.    The direction linemarking within the existing access,
           iii.   The widening of the current vehicle crossover, and
           iv.    Any works associated with the existing Telstra pit to the satisfaction of
                  Telstra. Suitable certification from Telstra shall be submitted to Council prior
                  to the commencement of any works and at the completion of the works.
         Further, a schedule of works, specifications and plans detailing this work shall be
         prepared and submitted to Council for approval as part of an application for
         Operational Works
     Pedestrian Access – Stage D
     70.   The pedestrian bridge (as annotated on the approved plans) cannot be constructed
           until a road closure approval has been obtained from the Department of Natural
           Resources and Mines. Council’s consent is to be obtained prior to the application
           being lodged with the Department.
     Stormwater Management – Stages C & D (Lot 3 RP264909)
     71.   The stormwater management design must be submitted with an Operational Works
           application and must demonstrate that the bioretention basin will only receive
           stormwater flows from catchments the bioretention basin is modelled to treat for water
           quality improvement purposes (i.e. Sub 2 as detailed on Figure 4 in the Stormwater
           Management Plan for Lot 4 Good Chap Street Noosaville by Aquaintel dated 25 June
           2017). Any detention area required for catchments that are not modelled to be treated
           by the bioretention basin, must be redirected around or under the bioretention basin.
     72.   Prior to commencement of use of any stage serviced by a stormwater quality treatment
           device, such as a bioretention basin, the Community Management Statement must be
           updated to identify and schedule the maintenance requirements for the stormwater
           quality treatment device asset for that relevant stage.
     73.   Vegetated stormwater quality treatment infrastructure must be maintained in
           accordance with the manufacturer’s specifications or for vegetated stormwater quality
           improvement assets, the Water by Design Guideline for Maintaining Vegetated
           Stormwater Assets
     Construction Management Plan – Stages C & D
     74.   A Construction Management Plan must be submitted to Council prior to a pre-start
           meeting and must specifically address the following:
           a.     Traffic Management during all aspects of the construction phase including:

                                                                                   Page 22 of 128
Log in to download the original file

2019-07-09 Planning & Environment Committee Agenda(PDF, 13MB).pdf · 13.2 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.